Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 7886751
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   Weekly report as on 28.01.2011
    
Progress Report For Mulankunnathukavu ROB for the week ending on 28-01-2011
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  Remarks 
1 PILE SHORNUR  SIDE 9 9 0 0 0 0 0 0  
2 PILE M.C SIDE 36 36 0 0 0 0 0 0  
3 PILE CAP SHORNUR SIDE 3 3 0 0 0 0 0 0  
4 PILE CAP  M.C SIDE 12 12 0 0 0 0 0 0  
5 PIER SHORNUR  SIDE 3 3 0 0 0 0 0 0  
6 PIER M.C SIDE 12 12 0 0 0 0 0 0  
7 PIER CAP SHORNUR  SIDE 3 0 3 0 0 0 0 1  
8 PIER CAP M.C SIDE 12 7 5 0 2 3 0 2  
9 RE/R WALL SHORNUR  SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%  
10 RE/R WALL M.C SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%  
11 BEAM/SLAB SHORNUR  SIDE 3 0 3 0 0 0 0 0  
12 BEAM/SLAB M.C SIDE 12 0 12 0 0 0 0 0  
13 HR/FP/KERB SHORNUR  SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%  
14 HR/FP/KERB M.C SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%  
15 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%   

 

 
Back
 
    
SHUTTERING AND REINFORCEMENT WORK OF PIERCAP P7

    
    
PIERCAP CONCRETING P7

    
    
PIERCAP P6 CONCRETING

    
    
SHUTTERING AND REINFORCEMENT WORK P5

    
 
    
PIERCAP P5 CONCRETING

    
    
COMPLETED PIERCAP

      
 

 

 

 

 

 

 

 

Untitled Document