Works completed as on 30th April 2015 | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
A. Over all Progress:-Following works are completed as on 30th April 2015 Pile 60/60, Pile load test 1/1, Pile cap 16/16, Pier 16/16, Pier Cap 16/16, Girders 13/16, Deckslab 12/16, RC wall Monthal side 50%, Culvert Monthal bridge side 100%, Drain Monthal bridge side 75%, Service road Monthal side 50%.
B. Progress of Monthly Target for April 2015
C.Target for May 2015
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||