Description
|
Completed/Progress
|
Remarks
|
|
ROB ALOOR-MALA
|
|
|
|
|
|
|
|
Piling
|
Completed.
|
completed 32/32
|
|
|
|
|
|
Pilecap
|
Completed.
|
COMPLETED 8OUT OF 8
|
|
|
|
|
|
Pier
|
Completed.
|
completed 6out of 6.
|
|
|
|
|
|
Piercap
|
Completed.
|
6 nos completed out of 6.
|
|
|
|
|
|
Girder
|
Completed
|
6 completed OUT OF 6
|
|
|
|
|
|
Slab
|
Completed
|
6 completed out of 6.
|
|
|
|
|
|
Handrail with kerb
|
started
|
Kerb 6 nos completed out of 6,Handrail 6 out of 6 completed.
|
|
|
|
|
|
Ex.joint
|
In progress
|
6 OUT OF 6
|
|
|
|
|
|
Tarring work
|
Not started
|
|
|
|
|
|
|
Diversion road
|
completed
|
aloor right side 100% completed.Mala side LHS 100%
|
|
|
|
|
|
Retaining wall work up to wall top
|
completed
|
Completed 4 sides.
|
|
|
|
|
|
Load test .
|
Completed.
|
In P4 location.
|
|
|
|
|
|
Service road work
|
In progress
|
Aloor side RHS,MALA side LHS ,Mala side RHS paver block laying completed.Aloor side LHS in progress.
|
|
Earth filling inside the approaches
|
completed
|
Completed
|
|
|
|
|
|
Under pass work
|
completed
|
Completed
|
|
|
|
|
|
Retaining wall kerb and handrail work aloor side .
|
completed
|
Aloor side 100% completed.
|
|
|
|
|
|
Retaining wall kerb and handrail work Mala side .
|
completed
|
Mala side 100 % completed.
|
|
|
|
|
|
Adjacent span P3 - RP2
|
In progress
|
Girder completed.Slab work in progress.
|
|
|
|
|
Adjacent span P2 - RP1
|
In progress
|
Girder completed.
|
|
|
|
|
GSB work in approach road aloor side
|
completed
|
Aloor side GSB completed
|
|
|
|
|
GSB work in approach road mala side
|
In progress
|
Mala side completed.
|
|
|
|
|
WMM work in approach road ALOOR side
|
|
Aloor side WMM completed
|
|
WMM work in approach road MALA side
|
|
Mala side WMM Iin progress.
|
|
|
|
|
|