   Weekly progress of Divine Nagar ROB as on 25.04.2015
    

All works except the works of adjacent spans connecting to railway span have been completed. The work of adjacent spans can be taken up only after the completion of railway span which is to be completed by Southern railways. The work of railway span is in progress. The pre-construction procedures for the construction adjacent spans are going on.

 