Prevoius Weekly Reports

   PROGRESS OF ROB ALOOR-MALA WORK AS ON 24-04-2015
    

 

Description

Completed/ Progress

Remarks

 

ROB ALOOR-MALA

 

 

1

Piling

Completed.

completed 32/32

2

Pilecap

Completed.

COMPLETED 8OUT OF 8

3

Pier

Completed.

completed 6out of 6.

4

Piercap

Completed.

6 nos completed out of 6.

5

Girder

Completed

6 completed OUT OF 6

6

Slab

Completed

6 completed out of 6.

7

Handrail with kerb

 started

Kerb 6 nos completed out of 6,Handrail 6 out of 6 completed.

8

Ex.joint

In progress

6 OUT OF 6

9

Tarring work

Not started

 

10

Diversion road

completed

aloor right side  100% completed.Mala side LHS 100%

11

Retaining wall work up to wall top

completed

Completed 4 sides.

12

Load test .

Completed.

In P4 location.

13

Service road work

 started

Aloor side RHS,MALA side LHS  ,Mala side RHS paver block laying completed.Aloor side LHS in progress.

14

Earth filling inside the approaches

 started

Completed

15

Under pass work

completed

Completed

16

Retaining wall kerb and handrail work aloor side .

completed

Aloor side 100% completed.

17

Retaining wall kerb and handrail work Mala  side .

completed

Mala side 100 % completed.

18

Adjacent span P3 - RP2

In progress

 Girder completed.

19

Adjacent span P2 - RP1

In progress

Shuttering in progress.

20

GSB work in approach road aloor side

completed

Aloor side GSB completed

 
Back
 
    
RP2-P3 SLAB WORK STARTED

    
    
PAVER BLOCK LAYING STARTED IN ALOOR SIDE LHS.

    
    
RP1-P2 GIRDER WORKS

    
    
GSB LEVELLING MALA SIDE APPROACH

    
 
    
ALOOR SIDE APPROACH

      
 

 

 

 

 

 

 

 