Prevoius Weekly Reports

   Progress Report of Eroor ROB as on 24.04.2015
    

Sl No.

Item Description

Unit

Rate

Estimated Qty

Estimated Amount (Rs)

Executed Qty

Executed Amount (Rs)

Work completed (%)

1

Pile

nos

458,294.21

38

17,415,180

19

8,707,590

50.0

2

Pilecap

nos

557,285.76

10

5,572,858

3

1,671,857

30.0

3

Pier

nos

208,982.16

10

2,089,822

3

626,946

30.0

4

Piercap

nos

348,303.60

10

3,483,036

1

348,304

10.0

 

                         Works during this week    

                              *    Reinforcement works for Pile cap

   

 

                              *    Staging and Reinforcement  works for Pier cap

   

 

                              *    Piling works on Tripunithura side.

   

 

 