   ROB at Angadipuram-Progress Report for the week ending 31.03.2015
    

Sl. No

 

Activity Description

Total Quantity

Cumulative progress up to last week

Balance  work up to last week

Cumulative delay in Qty up to last week

Work  planned  during the week

Actual work done during the week

Cumulative delay in Qty up to this week

Work  Planned for next week

No of days remaining for completion as per the weekly plan

1

Pile

56

56

0

0

0

0

0

0

 

2

Pilecap

18

13

5

0

0

0

0

0

 

3

Pier

18

11

7

1

1

0

1

2

6

4

Piercap

16

7

9

0

1

1

0

0

 

7

Girders

54

0

54

3

3

0

3

3

6

8

Deckslab

18

0

18

0

0

0

0

0

 

 
Back