   PROGRESS OF ROB ALOOR-MALA WORK AS ON 17-04-2015
    

 

PROGRESS OF ROB ALOOR-MALA WORK AS ON 17-04-2015.

 

Description

Completed/Progress

Remarks

 

1

ROB ALOOR-MALA

 

 

 

 

 

 

 

 

1

Piling

Completed.

completed 32/32

 

 

 

 

 

 

2

Pilecap

Completed.

COMPLETED 8OUT OF 8

 

 

 

 

 

 

3

Pier

Completed.

completed 6out of 6.

 

 

 

 

 

 

4

Piercap

Completed.

6 nos completed out of 6.

 

 

 

 

 

 

5

Girder

Completed

6 completed OUT OF 6

 

 

 

 

 

 

6

Slab

Completed

6 completed out of 6.

 

 

 

 

 

 

7

Handrail with kerb

started

Kerb 6 nos completed out of 6,Handrail 6 out of 6 completed.

 

 

 

 

 

 

8

Ex.joint

In progress

6 OUT OF 6

 

 

 

 

 

 

9

Tarring work

Not started

 

 

 

 

 

 

 

10

Diversion road

completed

aloor right side 100% completed.Mala side LHS 100%

 

 

 

 

 

 

11

Retaining wall work up to wall top

completed

Completed 4 sides.

 

 

 

 

 

 

12

Load test .

Completed.

In P4 location.

 

 

 

 

 

 

13

Service road work

started

Aloor side RHS,MALA side LHS ,Mala side RHS paver block laying

 

completed.Aloor side LHS balance.

 

 

 

 

 

 

 

 

 

 

14

Earth filling inside the approaches

started

Completed

 

 

 

 

 

 

15

Under pass work

completed

Completed

 

 

 

 

 

 

16

Retaining wall kerb and handrail work aloor side .

completed

Aloor side 100% completed.

 

 

 

 

 

 

17

Retaining wall kerb and handrail work Mala side .

completed

Mala side 100 % completed.

 

 

 

 

 

 

18

Adjacent span P3 - RP2

In progress

Girder concreted.

 

 

 

 

 

19

Adjacent span P2 - RP1

In progress

Rft work started.

 

 

 

 

 

20

GSB work in approach road aloor side

completed

Aloor side GSB completed

 

 

 

 

 

21

GSB work in approach road mala side

In progress

Mala side started.

 

 

 

 

 

 
Back
 
    
STRESSING-WORK-OF-RP2-P3-SPAN.

    
    
GSB-LAYING-IN-MALA-SIDE

    
    
APPROACH-SLAB-IN-A1.

    
    
ALOOR-SIDE-OF-ROB-FROM-RAILWAY-SPAN

    
 
    
ALOOR-SIDE-LHS-SERVICE-ROAD-WORK.

    
    
ALOOR-SIDE.

    
    
ADJ.SPAN-RP1-P2-RFT-WORK-IN-PROGRESS

    
 
 
 

 

 

 

 

 

 

 

Untitled Document