   Weekly progress as on 13.03.2015
    
Sl No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  Remarks 
1 PILE MONTHAL BRIDGE SIDE 33 33 0 9 0 0 9 0 Completed
2 PILE NH SIDE 27 27 0 2 0 0 2 0 Completed
3 PILE LOAD TEST 1 1 0 COMPLETE PILE LOAD TEST COMPLETE AT P15-1 LOCATION.
4 PILE CAP MONTHAL BRIDGE SIDE 9 8 1 2 0 0 1 0  
5 PILE CAP  NH SIDE 7 7 0 1 0 0 3 0  
6 PIER MONTHAL BRIDGE SIDE 9 8 1 1 1 0 3 1 P9 Planned
7 PIER NH SIDE 7 5 2   0 0   0  
8 PIER CAP MONTHAL BRIDGE  SIDE 9 8 1 1 0 0 2 0  
9 PIER CAP NH SIDE 7 6 1   1 0 1 1 P6 planned
10 RC WALL MONTHAL BRIDGE  SIDE 100% 50% 50% 10% 0% 0% 10% 0%  
11 RC  WALL NH SIDE 100% 0% 1            
12 GIRDER MONTHAL BRIDGE SIDE 9 7 2 1 0 0 2 0  
13 GIRDER NH SIDE 7 4 3   0 0 3 0  
14 DECK SLAB MONTHAL BRIDGE SIDE 9 7 2 0 0 0 1 0  
15 DECK SLAB NH SIDE 7 3 4   0 0   1 P3-P4 IP
16 EXPANSION JOINT MONTHAL BRIDGE SIDE 9 0 9            
17 EXPANSION JOINT NH SIDE 7 0 7            
18 KERB  MONTHAL BRIDGE  SIDE 9 6 3            
19 KERB NH SIDE 7 0 7            
20 HANDRAIL MONTHAL BRIDGE SIDE 9 0 9            
21 HANDRAIL NH SIDE 7 0 7            
22 Painting 100% 0% 100.00%            
23 ROAD WORK 100% 0% 100.00%            
24 BM/BC 100% 0% 100.00%            
25 Others/Miscellaneous   0 0            
26 Drainage + Culvert Monthal Side 100.00% 60.00% 40.00%   10.00% 5.00% 40.00% 10.00%  
                     
27 RAILWAY PORTION RP3 Pilecap done
                     
                     
                     
                     
  Availbility of Men                   
  Date 3/7/2015 3/8/2015 3/9/2015 3/10/2015 3/11/2015 3/12/2015 3/13/2015    
  No of labours 62 62 62 62 62 62 62    
 