   Weekly progress report as on 13.02.2015
    
PROGRESS OF ROB ALOOR-MALA  WORK AS ON 13-02-2015.
  Description Completed/ Progress Remarks
1 ROB ALOOR-MALA    
1 Piling Completed. completed 32/32
2 Pilecap Completed. COMPLETED 8OUT OF 8
3 Pier Completed. completed 6out of 6.
4 Piercap Completed. 6 nos completed out of 6.
5 Girder Completed 6 completed OUT OF 6
6 Slab Completed 6 completed out of 6.
7 Handrail with kerb  started Kerb 6 nos completed out of 6,Handrail 6 out of 6 completed.
8 Ex.joint In progress A1,A2, balance.
9 Tarring work Not started  
10 Diversion road completed aloor right side  100% completed.Mala side LHS 100%
11 Retaining wall work up to wall top completed Completed 4 sides.
12 Load test . Completed. In P4 location.
13 Service road work  started Aloor side RHS,MALA side LHS  ,Mala side RHS paver block laying completed.Aloor side LHS balance.
14 Earth filling inside the approaches  started Mala side in progress,Aloor side in progress.
15 Under pass work  completed Completed
16 Retaining wall kerb and handrail work aloor side . In progress Aloor side 100% completed.
17 Retaining wall kerb and handrail work Mala  side . In progress Mala side 50 % completed.
18 Adjacent span P3 - RP2 Started Ground levelling completed,staging started.
       
 