PROGRESS OF ROB ALOOR-MALA WORK AS ON 13-02-2015. |
|
|
Description |
Completed/ Progress |
Remarks |
|
1 |
ROB ALOOR-MALA |
|
|
|
1 |
Piling |
Completed. |
completed 32/32 |
|
2 |
Pilecap |
Completed. |
COMPLETED 8OUT OF 8 |
|
3 |
Pier |
Completed. |
completed 6out of 6. |
|
4 |
Piercap |
Completed. |
6 nos completed out of 6. |
|
5 |
Girder |
Completed |
6 completed OUT OF 6 |
|
6 |
Slab |
Completed |
6 completed out of 6. |
|
7 |
Handrail with kerb |
started |
Kerb 6 nos completed out of 6,Handrail 6 out of 6 completed. |
|
8 |
Ex.joint |
In progress |
A1,A2, balance. |
|
9 |
Tarring work |
Not started |
|
|
10 |
Diversion road |
completed |
aloor right side 100% completed.Mala side LHS 100% |
|
11 |
Retaining wall work up to wall top |
completed |
Completed 4 sides. |
|
12 |
Load test . |
Completed. |
In P4 location. |
|
13 |
Service road work |
started |
Aloor side RHS,MALA side LHS ,Mala side RHS paver block laying completed.Aloor side LHS balance. |
|
14 |
Earth filling inside the approaches |
started |
Mala side in progress,Aloor side in progress. |
|
15 |
Under pass work |
completed |
Completed |
|
16 |
Retaining wall kerb and handrail work aloor side . |
In progress |
Aloor side 100% completed. |
|
17 |
Retaining wall kerb and handrail work Mala side . |
In progress |
Mala side 50 % completed. |
|
18 |
Adjacent span P3 - RP2 |
Started |
Ground levelling completed,staging started. |
|
|
|
|
|