Sl No |
Activity Description |
Total Quantity |
Cumulative progress upto last week |
Balance work up to last week |
Cumulative delay in Qty up to last week |
Work planned during the week |
Actual work done during the week |
Cumulative delay in Qty up to this week |
Work Planned for next week |
Remarks |
1 |
PILE MONTHAL BRIDGE SIDE |
33 |
33 |
0 |
9 |
0 |
0 |
9 |
0 |
Completed |
2 |
PILE NH SIDE |
27 |
27 |
0 |
2 |
0 |
0 |
2 |
0 |
Completed |
3 |
PILE LOAD TEST |
1 |
1 |
0 |
COMPLETE |
PILE LOAD TEST COMPLETE AT P15-1 LOCATION. |
4 |
PILE CAP MONTHAL BRIDGE SIDE |
9 |
8 |
1 |
2 |
0 |
0 |
1 |
0 |
|
5 |
PILE CAP NH SIDE |
7 |
5 |
2 |
1 |
1 |
0 |
1 |
2 |
P5 and P6 |
6 |
PIER MONTHAL BRIDGE SIDE |
9 |
8 |
1 |
1 |
0 |
0 |
1 |
0 |
|
7 |
PIER NH SIDE |
7 |
5 |
2 |
|
0 |
0 |
|
0 |
|
8 |
PIER CAP MONTHAL BRIDGE SIDE |
9 |
8 |
1 |
1 |
0 |
0 |
2 |
0 |
|
9 |
PIER CAP NH SIDE |
7 |
4 |
3 |
|
0 |
0 |
|
0 |
|
10 |
RC WALL MONTHAL BRIDGE SIDE |
100% |
50% |
50% |
10% |
0% |
0% |
10% |
0% |
|
11 |
RC WALL NH SIDE |
100% |
0% |
100% |
|
|
|
|
|
|
12 |
GIRDER MONTHAL BRIDGE SIDE |
9 |
7 |
2 |
1 |
0 |
0 |
2 |
0 |
|
13 |
GIRDER NH SIDE |
7 |
0 |
7 |
|
0 |
0 |
|
1 |
A1-P1 |
14 |
DECK SLAB MONTHAL BRIDGE SIDE |
9 |
6 |
3 |
0 |
0 |
0 |
1 |
1 |
P16-A2 |
15 |
DECK SLAB NH SIDE |
7 |
0 |
7 |
|
|
|
|
|
|
16 |
EXPANSION JOINT MONTHAL BRIDGE SIDE |
9 |
0 |
9 |
|
|
|
|
|
|
17 |
EXPANSION JOINT NH SIDE |
7 |
0 |
7 |
|
|
|
|
|
|
18 |
KERB MONTHAL BRIDGE SIDE |
9 |
6 |
3 |
|
|
|
|
1 |
|
19 |
KERB NH SIDE |
7 |
0 |
7 |
|
|
|
|
|
|
20 |
HANDRAIL MONTHAL BRIDGE SIDE |
9 |
0 |
9 |
|
|
|
|
|
|
21 |
HANDRAIL NH SIDE |
7 |
0 |
7 |
|
|
|
|
|
|
22 |
Painting |
100% |
0% |
100.00% |
|
|
|
|
|
|
23 |
ROAD WORK |
100% |
0% |
100.00% |
|
|
|
|
|
|
24 |
BM/BC |
100% |
0% |
100.00% |
|
|
|
|
|
|
25 |
Others/Miscellaneous |
|
0 |
0 |
|
|
|
|
|
|
26 |
Drainage + Culvert Monthal Side |
100.00% |
15.00% |
85.00% |
|
|
|
|
10.00% |
|
|
|
|
|
|
|
|
|
|
|
|
27 |
RAILWAY PORTION |
RP3 Pilecap done |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Availbility of Men |
|
|
|
|
|
|
|
|
|
|
Date |
1/3/2015 |
1/4/2015 |
1/5/2015 |
1/6/2015 |
1/7/2015 |
1/8/2015 |
1/9/2015 |
|
|
|
No of labours |
54 |
54 |
54 |
54 |
54 |
54 |
54 |
|
|