   Weekly report as on 21.01.2011
    
SlNo  Activity -Description  Total Quantity  Cumulative progress up to this week -1 Balance  work -2 Cumulative delay in weeks after Spplagmnt -3 Work  planned  during the week -4 Actual work done during the last week -5 Short fall in the last week  -6 Work   Planned for next week -7 Remarks 
1 Re wall towards NH side  100% 0 100 18 0 0 0 0   
2 RE wall towards Pulikkakadavuside  100% 100 0 38 0 0 0   
3 Approach  5 No  4 1 27   
 Span 
4 Railway  3No  0 0 25               
 span 
5 Pile (Rly)pulikakadavu side  9 3 6 45  2  1   1    1    Earth Excavation of for piling at  P8 in progress
  
6 Pile (Rly)Nh side  9 0 9   2 0 2 2 Boring in progress 
6 Piers (Rly)  4No  0 0 35               
7    426m  217 209     55  60  -   60    
Handrail  
(in the pulikkakadavu side) 
  
8 Kerb  639m  268 371  70   0  52  70    
9 Road work  100% 0 0                  
10 Friction slab towards Pulikkakadavu side  128m  128      0 10 0 0     
11 Approachslab  2 No  1                     
     
12 Cap Beam  128m  128             0  0    
DATE 15/1/2011  17/1/2011  18/1/2011  19/1/2011  20/1/2011  21/1/2011         
Weather  Sunny  Sunny  Sunny Sunny   Sunny   Sunny         
Labour 14 26 28 35 31 31         
 
Back
 
    
WORK OF HAND RAIL 15.1.2011

    
    
WORK OF FRICTION SLAB 15.1.2011

    
    
WORK OF HAND RAIL 17.1.2011

    
    
WORK OF FRICTION SLAB 17.1.2011

    
 
    
PILE BORING 17.1.2011

    
    
XEN ,RAILWAYS VISITED THE SITE 19.1.2011

    
    
WORK OF FRICTION SLAB 19.1.2011

    
 
    
PILE CONCRETING 19.1.2011

    
    
EXCAVATION FOR PILE AT P8 19.01.2011

      
 

 

 

 

 

 

 

 