   weekly progress as on 19/12/2014
    
Sl. No. Item Description Unit Total Up to date  
Quantity Quantity  
1 Clearing and grubbing road land HA 3.9 2.962
3 Earthwork excavation at embankment foundation  Cum 30210 19225
4 Loosening, levelingand Compacting  Cum 1240 2437
5 Construction of sub-grade and earthen shoulders Cum 5290 1661
6 GSB (Grade I) Cum 8050 5289
7  Wet Mix Macadam (WMM) Cum 6900 3935
8 Primer coat (0.75KG/Sqm) Sqm 24370 13630
9 Tack coat Sqm 50230 48927
10 BM Cum 500 1047
11 DBM Cum 5790 3071
12 BC Cum 1260 0
13 Kerb stone Rm 8800 2383
 