   weekly progress as on 12.12.2014
    

 

Item Description Unit Original Quantity Upto Date Qty
Excavation for roadway        Cum 1320 3828.14053
Earthwork excavation at embankment foundation  Cum 30210 19737.61618
Loosening, leveling and Compacting        Cum 1240 2436.339377
GSB (Grade I) Cum 8050 5425.455213
 wet mix macadam (WMM) Cum 6900 4043
Primer coat (0.75KG/Sqm) Sqm 24370 15825.371
Tack coat (0.20kg/sqm) Sqm 50230 48928.006
BM (Bitumen 3.3%) Cum 500 922.2506667
DBM (Bitumen 4.25%) Cum 5790 2670.864575
BC (Bitumen 5.4%) Cum 1860 0
CC M25 for kerb stone       Rm 8800 3421.8
PCC M15 for sub-structure - for culverts , drain, utility duct etc  Cum 1050 587.52754
RCC M25 for  sub-structure/super structure etc for culverts , drain, utility duct Cum 5070 2211.372235
 HYSD bar reinforecement in sub -structure  MT 510 182.4508247
M20 grade concrete guard posts 200 x 200 mm x1.25 m Nos 550 169
Planting of trees by the road side  Nos 350 152
 