   Weekly progress report as on 17.10.2014
    
Progress Report For Kumaranalloore ROB for the week ending on 17-10-2014  
Sl No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE 33 33 0 0 0 0 0       pile completed
2 PILE CAP 11 11 0 0 0 0 0       pile cap completed
3 PIER 11 11 0 0 0 0 0      pier completed
4 PIER CAP 11 11 0 0 0 0 0      pier cap completed
5 LOAD TEST 1 1 0 0 0 0 0     Load test completed
6 SLAB 8 8 0 0 0 0 0     slabs completed
7 PEDESTAL 9 9 0 0 0 0 0     Pedestal completed
8 RETAINING WALL 4 4 0 0 0 0 0      Wall cornis portion left at kudamaloore side
9 ADJACENT SLAB 2 1 1 0 0.5 0 0 0.5   P6-RP2 slab reinforcement work
10- EXPANSION JIONTS 9 8 1 0 1 2 0     Expansion joint work started at Kudamaloor side
11 MISCELLANEOUS WORK 8 5 3 0 0 0 0 1   Handrail setting at Kudamaloor side
 