   Weekly progress report as on 03.10.2014
    
Progress Report For Angadipuram ROB for the week ending 03-10-2014
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan
1 Pile 56 40 16 0 3 2 1 4 6
2 Pilecap 18 0 18 0 1 0 0 1 6
3 Pier 18 2 16 0 0 0 0 0  
4 Piercap 16 0 16 1 1 1 0 0  
7 Girders 54 0 54 0 0 0 0 0  
8 Deckslab 18 0 18 0 0 0 0 0  
 