Prevoius Weekly Reports

   Weekly progress report as on 03.10.2014
    

 

PROGRESS OF ROB ALOOR-MALA  WORK AS ON 03-10-2014.
  Description Completed/ Progress Remarks
1 ROB ALOOR-MALA    
1 Piling Completed. completed 32/32
2 Pilecap Completed. COMPLETED 8OUT OF 8
3 Pier Completed. completed 6out of 6.
4 Piercap Completed. 6 nos completed out of 6.
5 Girder Completed 6 completed OUT OF 6
6 Slab Completed 6 completed out of 6.
7 Handrail with kerb  started Kerb 6 nos completed out of 6,Handrail 6 out of 6 completed.
8 Ex.joint In progress P4 only balance.
9 Tarring work Not started  
10 Diversion road completed aloor right side in progress 100% completed.Mala side LHS 100%
11 Retaining wall work up wall top In progress aloor side  completed  ,mala RHS wall 50m completed,LHS work in progress. 
12 Load test . Completed. In P4 location.
13 Service road work  started Aloor side LHS in progress.
 
Back
 
    
RP2 LOCATION DISTRUBED

    
    
RETAINING WALL WORK MALA SIDE LHS.

      
 

 

 

 

 

 

 

 