Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 8118757
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   Weekly progress as on 19.09.2014
    
 
Sl No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  Remarks 
1 PILE MONTHAL BRIDGE SIDE 33 24 9 9 0 0 9 0  
2 PILE NH SIDE 27 13 14 1 2 2 1 2 P3-2 ,P2-3 concreted.boring IP at P3-1 location.
3 PILE LOAD TEST 1 1 0 COMPLETE PILE LOAD TEST COMPLETE AT P15-1 LOCATION.
4 PILE CAP MONTHAL BRIDGE SIDE 9 6 3 2 0 0 1 0  
5 PILE CAP  NH SIDE 7 0 7            
6 PIER MONTHAL BRIDGE SIDE 9 6 3 1 0 0 1 0 No other locations.
7 PIER NH SIDE 7 0 7            
8 PIER CAP MONTHAL BRIDGE  SIDE 9 5 4 1 1 0 1 1 P10 planned
9 PIER CAP NH SIDE 7 0 7            
10 RC WALL MONTHAL BRIDGE  SIDE 100% 0% 1            
11 RC  WALL NH SIDE 100% 0% 1            
12 GIRDER MONTHAL BRIDGE SIDE 9 1 8 1 0 0 1 0 P13-P12 concreted.Staging IP for P13-P14 span.
13 GIRDER NH SIDE 7 0 7            
14 DECK SLAB MONTHAL BRIDGE SIDE 9 0 9 0 0 0 0 1 P13-P12 planned.
15 DECK SLAB NH SIDE 7 0 7            
16 EXPANSION JOINT MONTHAL BRIDGE SIDE 9 0 9            
17 EXPANSION JOINT NH SIDE 7 0 7            
18 KERB  MONTHAL BRIDGE  SIDE 9 0 9            
19 KERB NH SIDE 7 0 7            
20 HANDRAIL MONTHAL BRIDGE SIDE 9 0 9            
21 HANDRAIL NH SIDE 7 0 7            
22 Painting 100% 0% 100.00%            
23 ROAD WORK 100% 0% 100.00%            
24 BM/BC 100% 0% 100.00%            
25 Others/Miscellaneous   0 0            
26 Drainage  100.00% 0.00% 100.00%            
                     
27 RAILWAY PORTION WORK STARTED.RP1 PIERCAP CONCRETED.P8 piercap ip.
                     
                     
                     
                     
  Availbility of Men                   
  Date 9/13/2014 9/14/2014 9/15/2014 9/16/2014 9/17/2014 9/18/2014 9/19/2014    
  No of labours 40 32 41 40 41 42 42    
 
Back
 
    
P13-P12 SLAB REINF

    
    
P11,P10 PIER CAPS

      
 

 

 

 

 

 

 

 

Untitled Document