Prevoius Weekly Reports

   weekly progress as on 12.9.2014
    

 

Sl. No.

Item Description

Unit

Total

Quantity

Up to date   

Quantity   

1

Clearing and grubbing road land

HA

3.9

2.60

2

Excavation for roadway 

Cum

1320

900.00

3

Earthwork excavation at embankment foundation 

Cum

30210

16558.16

4

Loosening, leveling and Compacting 

Cum

1240

2106.18

5

Construction of sub-grade and earthen shoulders

Cum

5290

1638.90

6

GSB (Grade I)

Cum

8050

4110.55

7

 Wet Mix Macadam (WMM)

Cum

6900

2756.95

8

Primer coat (0.75KG/Sqm)

Sqm

24370

9817.55

9

Tack coat

Sqm

50230

36745.27

10

BM

Cum

500

647.00

11

DBM

Cum

5790

2021.17

12

Kerb stone

Rm

8800

2183.00

13

PCC M15 for sub-structure - for culverts , drain, utility duct etc 

Cum

1050

432.75

14

Tree planting

Nos

350

50.00

 
Back

No images are uploaded for this Weekly Reports

 
 
 

 

 

 

 

 

 

 