Sl. No.
|
Item Description
|
Unit
|
Total
Quantity
|
Up to date
Quantity
|
1
|
Clearing and grubbing road land
|
HA
|
3.9
|
2.60
|
2
|
Excavation for roadway
|
Cum
|
1320
|
900.00
|
3
|
Earthwork excavation at embankment foundation
|
Cum
|
30210
|
16558.16
|
4
|
Loosening, leveling and Compacting
|
Cum
|
1240
|
2106.18
|
5
|
Construction of sub-grade and earthen shoulders
|
Cum
|
5290
|
1638.90
|
6
|
GSB (Grade I)
|
Cum
|
8050
|
4110.55
|
7
|
Wet Mix Macadam (WMM)
|
Cum
|
6900
|
2756.95
|
8
|
Primer coat (0.75KG/Sqm)
|
Sqm
|
24370
|
9817.55
|
9
|
Tack coat
|
Sqm
|
50230
|
36745.27
|
10
|
BM
|
Cum
|
500
|
647.00
|
11
|
DBM
|
Cum
|
5790
|
2021.17
|
12
|
Kerb stone
|
Rm
|
8800
|
2183.00
|
13
|
PCC M15 for sub-structure - for culverts , drain, utility duct etc
|
Cum
|
1050
|
432.75
|
14
|
Tree planting
|
Nos
|
350
|
50.00
|
|