   weekly progress as on 22.8.2014
    
 

SlNo

Item Description

Unit

Estimated

Quantity

Up to date

Quantity

1

Clearing and grubbing road land

HA

3.9

2.27

2

Excavation for roadway 

Cum

1320

2221.44

3

Earthwork excavation at embankment foundation 

Cum

30210

11108.16

4

Loosening, levelingand Compacting 

Cum

1240

1066.18

5

Construction of sub-grade and earthen shoulders

Cum

5290

1638.90

6

GSB (Grade I)

Cum

8050

3670.55

7

 Wet Mix Macadam (WMM)

Cum

6900

2491.95

8

Primer coat (0.75KG/Sqm)

Sqm

24370

8354.55

9

Tack coat

Sqm

50230

35217.27

10

BM

Cum

500

647.00

11

DBM

Cum

5790

2021.17

12

BC

Cum

1260

0.00

13

Kerb stone

Rm

8800

1835.00

14

Construction of embankment (road way cutting material)

Cum

3890

1735.68

15

PCC M15 for sub-structure - for culverts , drain, utility duct etc 

Cum

1050

367.75

16

PCC M25 for  sub-structure/super structure etc for culverts , drain, utility duct

Cum

5070

1640.42

17

 HYSD bar reinforecemntin sub -structure 

MT

510

165.47

18

M20 grade concrete guard posts 200 x 200 mm x1.25 m

Nos

550

57.00

19

Tree planting

Nos

350

0.00

 