Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 7888066
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   weekly progress 14.01.2011
    

 

SlNo

Activity -Description

Total Quantity

Cumulative progress up to this week

(1)

Balance  work

(2)

Cumulative delayin weeks after

Spplagmnt

(3)

Work  planned  during the week

(4)

Actual work done during the last week

(5)

Short fall in the last week 

(6)

Work  Planned for next week

(7)

Remarks

1

Re wall towards NH side

100%

0

100

17

0

0

0

0

 

2

RE wall towards Pulikkakadavuside

100%

99

2

37

1

1

-

1

 

3

Approach

 Span

5 No

4

1

26

-

-

-

-

 

4

Railway

 span

3No

0

0

24

 

 

 

 

 

5

Pile (Rly)

18No

2 Pile on Pulikkakadavu side completed and boring of one pile is in progress.

Boring of one pile on Nh side started but work held up

 

17

44

 

 

 

 Pile concreting of P1B4,P2B2,P2B1,P1B3

 

6

Piers (Rly)

4No

0

0

34

 

 

 

 

 

7

 

Handrail (in the pulikkakadavu side)

 

426m

157

269

 

 55

15

 40

 60

 

8

Kerb

639m

248

391

-

 70

 0

70

 70

 

9

Road work

100%

0

0

 

 

 

 

 

 

10

Friction slab towards Pulikkakadavu side

128m

118

10

 

55

55

 

 10

 

11

Approachslab

 

2 No

1

 

 

 

 

 

 

 

 

12

Cap Beam

128m

128

 

 

 20

 20

0

 0

 

 

Date

08-1-2011

10-01-2011

11-01-2011

12-01-2011

13-01-2011

14-1-2011

 

 

 

 

 

Climate

Sunny

Sunny

Sunny

Sunny

pleasant

 

sunny

 

 

 

 

 

Labour (no)

   27

26

24

20

21

21

 

 

 

  

 
Back
 
    
HAND RAIL IS IN PROGRESS 8.1.2011

    
    
FRICTION SLAB IS IN PROGRESS 8.1.2011

    
    
WORK OF HAND RAIL IS IN PROGRESS 10.1.2011

    
    
WORK OF FRICTION SLAB IS IN PROGRESS 10.1.2011

    
 
    
LOWERING OF PILE REINFORCEMNET 11.1.2011

    
    
PILING ON NH SIDE STARTED 13.1.2011

    
    
EXCAVATION FOR RE WALL ON NH SIDE STARTED 13.1.2011

    
 
    
WORK OF PILE FOR PIER P2 - 14.1.2011

    
    
WORK OF FRICTION SLAB IS IN PROGRESS 14.1.2011

      
 

 

 

 

 

 

 

 

Untitled Document