   weekly progress as on 1.8.2014
    

 

SlNo  Item Description  Unit  Estimated Quantity Up to date   Quantity Work Planned for  August 
1 Clearing and grubbing road land  HA  3.9 2.27 0.2
2 Excavation for roadway   Cum  1320 2221.44 60
3 Earthwork excavation at embankment foundation   Cum  30210 11108.16 450
4 Loosening, leveling and Compacting   Cum  1240 1066.18 150
5 Construction of sub-grade and earthen shoulders  Cum  5290 1638.9 200
6 GSB (Grade I)  Cum  8050 3670.55 200
7  Wet Mix Macadam (WMM)  Cum  6900 2491.95 250
8 Primer coat (0.75KG/Sqm)  Sqm  24370 8354.55 1500
9 Tack coat Sqm  50230 35217.27 8000
10 BM  Cum  500 647 60
11 DBM  Cum  5790 2021.17 450
12 BC Cum  1260 0 350
13 Kerb stone  Rm 8800 1835 300
14 Construction of embankment (road way cutting material)  Cum  3890 1735.68 60
15 PCC M15 for sub-structure - for culverts , drain, utility duct etc   Cum  1050 367.75 30
16 PCC M25 for  sub-structure/super structure etc for culverts , drain, utility duct  Cum  5070 1640.42 40
17  HYSD bar reinforecemnt in sub -structure   MT  510 165.47 3
18 M20 grade concrete guard posts 200 x 200 mm x1.25 m  Nos  550 57 0
19 Tree planting  Nos  350 0 70
 