   Weekly progress report as on 18.07.2014
    
PROGRESS OF ROB ALOOR-MALA  WORK AS ON 18-07-2014.
  Description Completed/ Progress Remarks
1 ROB ALOOR-MALA    
1 Piling Completed. completed 32/32
2 Pilecap Completed. COMPLETED 8OUT OF 8
3 Pier Completed. completed 6out of 6.
4 Piercap Completed. 6 nos completed out of 6.
5 Girder In progress 6 completed OUT OF 6
6 Slab In progress 5 completed out of 6.
7 Handrail with kerb  started Kerb 5 nos completed out of 6.(kerb only)
8 Ex.joint Not started  
9 Tarring work Not started  
10 Diversion road  In Progress aloor right side in progress 100% completed.Mala side LHS 100%
11 Retaining wall worK  started aloor side LHS completed,RHS 70 % completed and in progress   ,mala RHS WALL 50 M COMPLETED. 
12 Load test . Completed. In P4 location.
13 Service road work  started Aloor side LHS in progress.
       
       
       
       
       
       
 
Back
 
    
P5-P6 SLAB STAGING STARTED.

    
    
DECK SLAB WORK IN P5-P6.

    
    
DECK SLAB WORK IN P5-P6.

      
 

 

 

 

 

 

 

 