Prevoius Weekly Reports

   Weekly report as on 07.01.2011
    
Progress Report For Mulankunnathukavu ROB for the week ending on 07-01-2011
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  Remarks 
1 PILE SHORNUR  SIDE 9 9 0 0 0 0 0 0  
2 PILE M.C SIDE 36 36 0 0 0 0 0 0  
3 PILE CAP SHORNUR SIDE 3 1 2 0 0 2 0 0  
4 PILE CAP  M.C SIDE 12 12 0 0 0 0 0 0  
5 PIER SHORNUR  SIDE 3 0 3 0 0 3 0 0  
6 PIER M.C SIDE 12 9.5 2.5 0.5 2 2.5 0 0  
7 PIER CAP SHORNUR  SIDE 3 0 3 0 0 0 0 0  
8 PIER CAP M.C SIDE 12 0 12 0 2 0 2 2  
9 RE/R WALL SHORNUR  SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%  
10 RE/R WALL M.C SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%  
11 BEAM/SLAB SHORNUR  SIDE 3 0 3 0 0 0 0 0  
12 BEAM/SLAB M.C SIDE 12 0 12 0 0 0 0 0  
13 HR/FP/KERB SHORNUR  SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%  
14 HR/FP/KERB M.C SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%  
15 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%   

 

 
Back
 
    
PILE CAP P2 CONCRETING - 01.01.2011

    
    
PILE CAP AP1 CONCRETING - 02.01.2011

    
    
FORM WORK FOR PIER CAP 03.01.2011

    
    
STAGING WORK FOR PIER CAP CONCRETING - 04.01.2011

    
 
    
REINFORCEMENT WORK FOR PIER CAP - 05.01.2011

    
    
COMPLETED PIERS TO MEDICAL COLLEGE SIDE - 06.01.2011

    
    
PIER CAP CONCRETING - 07.01.2011

    
 
 
 

 

 

 

 

 

 

 