   weekly progress as on 4.7.2014
    

 

SlNo

Item description

Unit

Estimated quantity

Executed Quantity

1

Clearing and grubbing road land

HA

3.9

2.22

9

Excavation for roadway 

Cum

1320

2109.10

10

Earthwork excavation at embankment foundation 

Cum

30210

10037.60

11

Loosening, leveling and Compacting 

Cum

1240

870.18

12

Construction of sub-grade and earthen shoulders

Cum

5290

1008.90

13

GSB (Grade I)

Cum

8050

3281.55

14

 Wet Mix Macadam (WMM)

Cum

6900

2291.95

15

Primer coat (0.75KG/Sqm)

Sqm

24370

8354.55

16

Tack coat

Sqm

50230

35217.27

17

BM

Cum

500

647.00

18

DBM

Cum

5790

2021.17

19

Kerb stone

Rm

8800

240.00

20

Construction of embankment (road way cutting material)

Cum

3890

1035.68

21

PCC M15 for sub-structure - for culverts , drain, utility duct etc 

Cum

1050

287.75

22

PCC M25 for  sub-structure/super structure etc for culverts , drain, utility duct

Cum

5070

1408.42

23

 HYSD bar reinforecemnt in sub -structure 

MT

510

146.47

24

M20 grade concrete guard posts 200 x 200 mm x1.25 m

Nos

550

57.00

 