   Weekly Progress Report as on 27.06.2014
    
Sl No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  Remarks 
1 PILE CHERUVATHOOR  SIDE 27 27 Completed  
2 PILE PADANNA SIDE 24 24 Completed  
3 PILE CAP CHERUVATHOOR SIDE 9 9 Completed  
4 PILE CAP  PADANNA SIDE 8 8 Completed  
5 PIER CHERUVATHOOR SIDE 9 9 Completed  
6 PIER PADANNA SIDE 8 8 Completed  
7 PIER CAP CHERUVATHOOR SIDE 9 9 Completed  
8 PIER CAP PADANNA SIDE 8 8 Completed  
9 RE/RC WALL CHERUVATHOOR  SIDE 100% 100% Completed  
10 RE/RC  WALL PADANNA SIDE 100% 100% Completed  
11 BEAM/SLAB CHERUVATHOOR  SIDE 9 9 Completed RP3-P8 adjacent span girder and slab concreted.
12 BEAM/SLAB PADANNA SIDE 8 8 Completed RP1-P7 Adjacent span GIRDER AND SLAB CONCRETED.
13 EXPANSION JOINT CHERUVATHUR SIDE 9 9 Completed P8 and RP3 concreted.
14 EXPANSION JOINT PADANNA SIDE 8 7 Completed P7 and RP1 concreted.
15 KERB CHERUVATHOOR  SIDE 100% 100.00% Completed  RP3-P8 SPAN KERB CONCRETED.
16 KERB PADANNA SIDE 100% 100% Completed RP1-P7 SPAN KERB CONCRETED.
17 HANDRAIL CHERUVATHUR SIDE 100% 100% Completed  RP3-P8 SPAN HANDRAIL CONCRETED.
18 HANDRAIL PADANNA SIDE 100% 100% Completed RP1-P7 span concreted.
19 Painting 100% 95% Completed Painting complete except adjacent span.
17 BM/BC 100% 90% 10% 10% 10.00% 8.00% 2.00% 2.00% Padanna service road DBM/BC done.Adjacent spans wearing coat remaining.
18 Others/Miscellaneous                  
19 ROAD WORK GSB+WMM Work 100% complete  
20 Drainage Padanna side 100.00% 98.00% 2.00% 2.00% 0.00% 0.00% 2.00% 0.00% Drainage works 3m remaining.
                    DR Work complete for 4m service road and 7m road chr side.
21 RAILWAY PORTION ENTIRE WORKS COMPLETE EXCEPT PAINTING.PAINTING 50% COMPLETE.
                    Hume pipe laying complete at chr side to drain off rain water
 