Sl No |
Activity Description |
Total Quantity |
Cumulative progress upto last week |
Balance work up to last week |
Cumulative delay in Qty up to last week |
Work planned during the week |
Actual work done during the week |
Cumulative delay in Qty up to this week |
Work Planned for next week |
Remarks |
1 |
PILE CHERUVATHOOR SIDE |
27 |
27 |
Completed |
|
2 |
PILE PADANNA SIDE |
24 |
24 |
Completed |
|
3 |
PILE CAP CHERUVATHOOR SIDE |
9 |
9 |
Completed |
|
4 |
PILE CAP PADANNA SIDE |
8 |
8 |
Completed |
|
5 |
PIER CHERUVATHOOR SIDE |
9 |
9 |
Completed |
|
6 |
PIER PADANNA SIDE |
8 |
8 |
Completed |
|
7 |
PIER CAP CHERUVATHOOR SIDE |
9 |
9 |
Completed |
|
8 |
PIER CAP PADANNA SIDE |
8 |
8 |
Completed |
|
9 |
RE/RC WALL CHERUVATHOOR SIDE |
100% |
100% |
Completed |
|
10 |
RE/RC WALL PADANNA SIDE |
100% |
100% |
Completed |
|
11 |
BEAM/SLAB CHERUVATHOOR SIDE |
9 |
9 |
Completed |
RP3-P8 adjacent span girder and slab concreted. |
12 |
BEAM/SLAB PADANNA SIDE |
8 |
8 |
Completed |
RP1-P7 Adjacent span GIRDER AND SLAB CONCRETED. |
13 |
EXPANSION JOINT CHERUVATHUR SIDE |
9 |
9 |
Completed |
P8 and RP3 concreted. |
14 |
EXPANSION JOINT PADANNA SIDE |
8 |
7 |
Completed |
P7 and RP1 concreted. |
15 |
KERB CHERUVATHOOR SIDE |
100% |
100.00% |
Completed |
RP3-P8 SPAN KERB CONCRETED. |
16 |
KERB PADANNA SIDE |
100% |
100% |
Completed |
RP1-P7 SPAN KERB CONCRETED. |
17 |
HANDRAIL CHERUVATHUR SIDE |
100% |
100% |
Completed |
RP3-P8 SPAN HANDRAIL CONCRETED. |
18 |
HANDRAIL PADANNA SIDE |
100% |
100% |
Completed |
RP1-P7 span concreted. |
19 |
Painting |
100% |
95% |
Completed |
Painting complete except adjacent span. |
17 |
BM/BC |
100% |
90% |
10% |
10% |
10.00% |
8.00% |
2.00% |
2.00% |
Padanna service road DBM/BC done.Adjacent spans wearing coat remaining. |
18 |
Others/Miscellaneous |
|
|
|
|
|
|
|
|
|
19 |
ROAD WORK |
GSB+WMM Work 100% complete |
|
20 |
Drainage Padanna side |
100.00% |
98.00% |
2.00% |
2.00% |
0.00% |
0.00% |
2.00% |
0.00% |
Drainage works 3m remaining. |
|
|
|
|
|
|
|
|
|
|
DR Work complete for 4m service road and 7m road chr side. |
21 |
RAILWAY PORTION |
ENTIRE WORKS COMPLETE EXCEPT PAINTING.PAINTING 50% COMPLETE. |
|
|
|
|
|
|
|
|
|
|
Hume pipe laying complete at chr side to drain off rain water |