Prevoius Weekly Reports

   weekly progress as on 7.1.2010
    

 

SlNo  Activity -Description  Total Quantity  Cumulative progress up to this week  Balance   work Cumulative delay in weeks after suppl agmt Work  planned  during the week  Actual work done during the last week  Short fall in the last week   Work  Planned for next week 
1 Re wall towards NH side  100% 0 100 17 0 0 0 0
2 RE wall towards Pulikkakadavuside  100% 100 0 37     0
3 Approachspan 5 No  4 1 26
4 Railwayspan 3No  0 0 24            
5 Pile (Rly)  18No   21.64 m   17 44           Piling Concrete 
6 Piers (Rly)  4No  0 0 34            
  Handrail (in the Pulikkakadavu side)                 
8 Kerb  639m  248 391  70   0      70 
9 Road work  100% 0 0               
10 Friction slab towards Pulikkakadavu side  128m  55 73    15 15 0  55m 
11 Approachslab  2 No  1                  
12 Cap Beam  128m  108  20      20   0      20 
 
Back
 
    
HAND RAIL WORK IS IN PROGRESS 4.1.2011

    
    
HAND RAIL WORK IS IN PROGRESS 1.1.2011

    
    
HAND RAIL WORK IS IN PROGRESS 7.1.2010

    
    
WORK OF FRICTION SLAB 6.1.2011.

    
 
    
FRICTION SLAB 5.1.2011

    
    
FRICTION SLAB REMAINIG 5.1.2011

    
    
ERRECTING PILE REINFORCEMENT 4.1.2011

    
 
    
PILE CONCRETING 5.1.2011

      
 

 

 

 

 

 

 

 