   Weekly Progress Report as on 13.06.2014
    
Sl No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  Remarks 
1 PILE CHERUVATHOOR  SIDE 27 27 Completed  
2 PILE PADANNA SIDE 24 24 Completed  
3 PILE CAP CHERUVATHOOR SIDE 9 9 Completed  
4 PILE CAP  PADANNA SIDE 8 8 Completed  
5 PIER CHERUVATHOOR SIDE 9 9 Completed  
6 PIER PADANNA SIDE 8 8 Completed  
7 PIER CAP CHERUVATHOOR SIDE 9 9 Completed  
8 PIER CAP PADANNA SIDE 8 8 Completed  
9 RE/RC WALL CHERUVATHOOR  SIDE 100% 100% Completed  
10 RE/RC  WALL PADANNA SIDE 100% 100% Completed  
11 BEAM/SLAB CHERUVATHOOR  SIDE 9 9 Completed RP3-P8 adjacent span girder and slab concreted.
12 BEAM/SLAB PADANNA SIDE 8 7 1 complete except railway adjacent span RP1-P7 Adjacent span GIRDER  CONCRETED on 04.06.14.
13 EXPANSION JOINT CHERUVATHUR SIDE 9 9 Completed P8 location concreted this week.
14 EXPANSION JOINT PADANNA SIDE 8 7 1 0 0 0 0 0 complete except P7
15 KERB CHERUVATHOOR  SIDE 100% 100.00% Completed  RP3-P8 SPAN KERB CONCRETED.
16 KERB PADANNA SIDE 100% 100% complete except railway adjacent span  
17 HANDRAIL CHERUVATHUR SIDE 100% 100% Completed  RP3-P8 SPAN HANDRAIL CONCRETED.
18 HANDRAIL PADANNA SIDE 100% 100% complete except railway adjacent span  
19 Painting 100% 100% Completed Painting complete except adjacent span.
17 BM/BC 100% 90% 10% 10% 0.00% 0.00% 10.00% 0.00% Bitumen works complete except Padanna side 4m road .
18 Others/Miscellaneous                  
19 ROAD WORK GSB+WMM Work 100% complete  
20 Drainage Padanna side 100.00% 98.00% 2.00% 2.00% 0.00% 0.00% 2.00% 0.00% Drainage works 3m remaining.
                    DR Work complete for 4m service road and 7m road chr side.
21 RAILWAY PORTION ENTIRE WORKS COMPLETE EXCEPT WEARING COAT,FOOT PATH SLAB AND PAINTING.
                    Hume pipe laying complete at chr side to drain off rain water
 
Back
 
    
RP1-P7 DECK SLAB READY FOR CONCRETE

      
 

 

 

 

 

 

 

 