   Weekly Progress report as on 07/01/2011
    

 

Progress Report For Kainatty ROB for the week ending on 7-01-2011

Si No

Activity Description

Total Quantity

Cumulative progress upto last week

Balance  work up to last week

Cumulative delay in Qty up to last week

Work  planned  during the week

Actual work done during the week

Cumulative delay in Qty up to this week

Work  Planned for next week

Remarks

1

PILE KAINATTY  SIDE

18

12

6

3

3

1

5

0

 

2

PILE NADAPURAM SIDE

27

16

11

0

3

2

*0

3

*work done earlier

3

PILE CAP KAINATTY SIDE

6

0

6

2

1

0

3

1

 

4

PILE CAP  NADAPURAM SIDE

9

0

9

1

0

0

1

1

 

5

PIER KAINATTY  SIDE

6

0

6

1

1

0

2

0

 

6

PIER NADAPURAM SIDE

9

0

9

0

0

0

0

1

 

7

PIER CAP KAINATTY  SIDE

6

0

6

0

0

0

0

1

 

8

PIER CAP NADAPURAM SIDE

9

0

9

0

0

0

0

0

 

 
Back
 
    
CONSTRUCTION EQUIPMENTS (06/01/2011)

    
    
PIPE LINE ROAD (05/01/2011)

    
    
OFC CABLES TO BE SHIFTED (05/01/2011)

    
    
REMOVING OF TREES FROM THE ALINGMENT OF ROB (05/01/2011)

    
 
    
REMOVING OF TREES FROM THE ALINGMENT OF ROB (05/01/2011)

    
    
REINFORCEMENT WORKS IN PROGRESS (05/01/2011)

    
    
EARTH FILLING AT KAINATTY SIDE (05/01/2011)

    
 
 
 

 

 

 

 

 

 

 