   Weekly progress report as on 13.06.2014
    
Progress Report For Edapalam Moorkanad River Bridge for the week ending 13-06-2014  
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 Pile 56 3 53 0 3 3 0 2 6  
2 Pilecap 16 0 0 0 0 0 0 1 6  
3 Pier 16 0 0 0 0 0 0 0    
4 Piercap 16 0 0 0 0 0 0 0    
5 Abutment 2 0 0 0 0 0 0 0    
6 Abutment cap 2 0 0 0 0 0 0 0    
7 Girders 54 0 0 0 0 0 0 0    
8 Deckslab 18 0 0 0 0 0 0 0    
 
Back
 
    
P16C PILE CONCRETING IN PROGRESS

      
 

 

 

 

 

 

 

 