Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 7888280
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   weekly progress as on 31.12.2010
    

 

SlNo

Activity -Description

Total Quantity

Cumulative progress up to this week

(1)

Balance  work

(2)

Cumulative delayinweeks after

Spplagmnt

(3)

Work  planned  during the week

(4)

Actual work done during the last week

(5)

Short fall in the last week 

(6)

Work  Planned for next week

(7)

1

Re wall towards NH side

100%

0

100

17

0

0

0

0

2

RE wall towards Pulikkakadavuside

100%

100

0

37

 

 

-

0

3

Approach

 Span

5 No

4

1

26

-

-

-

-

4

Railway

 span

3No

0

0

24

 

 

 

 

5

Pile (Rly)

18No

 21.64 m

17

44

 

 

 

 Piling Concrete

6

Piers (Rly)

4No

0

0

34

 

 

 

 

7

 

Handrail (in the Pulikkakadavuside)

 

426m

102

324

 

 

 15

 0

 60m

8

Kerb

639m

248

391

-

 

 29

 

 70

9

Road work

100%

0

0

 

 

 

 

 

10

Friction slab towards Pulikkakadavu side

128m

55

73

 

15

15

0

 55m

11

Approachslab

 

2 No

1

 

 

 

 

 

 

 

12

CapBeam

128m

108

 20

 

 

 

 

 20

 

    

Date

27-12-2010

28-12-2010

29-12-2010

30-12-2010

31-12-2010

Climate

Sunny

Pleasant

Pleasant

Sunny

Sunny

Labour(no)

   19

    21

20

22

24

               
                   
                   
 
Back
 
    
HAND RAIL IS IN PROGRESS1

    
    
PILING WORK IS IN PROGRESS 31.12.2010

      
 

 

 

 

 

 

 

 