   Weekly report as on 31.12.2010
    
Progress Report For Kainatty ROB for the week ending on 31-12-2010
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  Remarks 
1 PILE KAINATTY  SIDE 18 11 7 3 0 1 2 3  
2 PILE NADAPURAM SIDE 27 15 12 0 6 1 *0 3 *work done earlier
3 PILE CAP KAINATTY SIDE 6 0 6 2 0 0 2 0  
4 PILE CAP  NADAPURAM SIDE 9 0 9 0 1 0 1 0  
5 PIER KAINATTY  SIDE 6 0 6 1 0 0 1 1  
6 PIER NADAPURAM SIDE 9 0 9 0 0 0 0 0  
7 PIER CAP KAINATTY  SIDE 6 0 6 0 0 0 0 0  
8 PIER CAP NADAPURAM SIDE 9 0 9 0 0 0 0 0  
9 RE/R WALL KAINATTY  SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%  
10 RE/R WALL NADAPURAM SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%  
11 BEAM/SLAB KAINATTY  SIDE 6 0 6 0 0 0 0 0  
12 BEAM/SLAB NADAPURAM SIDE 9 0 9 0 0 0 0 0  
13 HR/FP/KERB KAINATTY  SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%  
14 HR/FP/KERB NADAPURAM SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%  
15 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%   

 

 
Back
 
    
PREPARATION FOR PILING - 29.12.2010

    
    
PILING - 30.12.2010

    
    
CUBE TEST - 30.12.2010

    
    
PILE P11 - 1 CONCREING - 31.12.2010

    
 
    
PILE P11 - 1 CONCREING - 31.12.2010

      
 

 

 

 

 

 

 

 