Sl No |
Activity Description |
Total Quantity |
Cumulative progress upto last week |
Balance work up to last week |
Cumulative delay in Qty up to last week |
Work planned during the week |
Actual work done during the week |
Cumulative delay in Qty up to this week |
Work Planned for next week |
Remarks |
1 |
PILE CHERUVATHOOR SIDE |
27 |
27 |
Completed |
|
2 |
PILE PADANNA SIDE |
24 |
24 |
Completed |
|
3 |
PILE CAP CHERUVATHOOR SIDE |
9 |
9 |
Completed |
|
4 |
PILE CAP PADANNA SIDE |
8 |
8 |
Completed |
|
5 |
PIER CHERUVATHOOR SIDE |
9 |
9 |
Completed |
|
6 |
PIER PADANNA SIDE |
8 |
8 |
Completed |
|
7 |
PIER CAP CHERUVATHOOR SIDE |
9 |
9 |
Completed |
|
8 |
PIER CAP PADANNA SIDE |
8 |
8 |
Completed |
|
9 |
RE/RC WALL CHERUVATHOOR SIDE |
100% |
100% |
Completed |
|
10 |
RE/RC WALL PADANNA SIDE |
100% |
100% |
Completed |
|
11 |
BEAM/SLAB CHERUVATHOOR SIDE |
9 |
9 |
Completed |
RP3-P8 adjacent span girder and slab concreted. |
12 |
BEAM/SLAB PADANNA SIDE |
8 |
7 |
1 |
complete except railway adjacent span |
RP1-P7 Adjacent span GIRDER CONCRETED on 04.06.14. |
13 |
EXPANSION JOINT CHERUVATHUR SIDE |
9 |
9 |
Completed |
P8 location concreted this week. |
14 |
EXPANSION JOINT PADANNA SIDE |
8 |
7 |
1 |
0 |
0 |
0 |
0 |
0 |
complete except P7 |
15 |
KERB CHERUVATHOOR SIDE |
100% |
100.00% |
Completed |
RP3-P8 SPAN KERB CONCRETED. |
16 |
KERB PADANNA SIDE |
100% |
100% |
complete except railway adjacent span |
|
17 |
HANDRAIL CHERUVATHUR SIDE |
100% |
100% |
complete except railway adjacent span |
|
18 |
HANDRAIL PADANNA SIDE |
100% |
100% |
complete except railway adjacent span |
|
19 |
Painting |
100% |
100% |
Completed |
Painting complete except adjacent span. |
17 |
BM/BC |
100% |
90% |
10% |
10% |
0.00% |
0.00% |
10.00% |
0.00% |
Bitumen works complete except Padanna side 4m road . |
18 |
Others/Miscellaneous |
|
|
|
|
|
|
|
|
|
19 |
ROAD WORK |
GSB+WMM Work 100% complete |
|
20 |
Drainage Padanna side |
100.00% |
98.00% |
2.00% |
2.00% |
0.00% |
0.00% |
2.00% |
0.00% |
Drainage works 3m remaining. |
|
|
|
|
|
|
|
|
|
|
DR Work complete for 4m service road and 7m road chr side. |
21 |
RAILWAY PORTION |
ENTIRE WORKS COMPLETE EXCEPT WEARING COAT,FOOT PATH SLAB AND PAINTING. |
|
|
|
|
|
|
|
|
|
|
Hume pipe laying complete at chr side to drain off rain water |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Availbility of Men |
|
|
|
|
|
|
|
|
|
|
Date |
5/31/2014 |
6/1/2014 |
6/2/2014 |
6/3/2014 |
6/4/2014 |
6/5/2014 |
6/6/2014 |
|
|
|
No of labours |
21 |
21 |
10 |
7 |
12 |
12 |
12 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Material Stocking Status |
Required |
Available |
Remarks |
|
|
|
|
|
|
|
Coarse Aggreagate (m3) |
available |
|
|
|
|
|
|
|
|
Fine Aggreagate(m3) |
available |
|
|
|
|
|
|
|
Cement(bag) |
RMC |
|
|
|
|
|
|
Steel(MT) |
5 |
2 |
shortage at site |
|
|
|
|
|