Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 8052834
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   Weekly Progress Report as on 02.05.2014
    
Sl No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  Remarks 
1 PILE CHERUVATHOOR  SIDE 27 27 Completed  
2 PILE PADANNA SIDE 24 24 Completed  
3 PILE CAP CHERUVATHOOR SIDE 9 9 Completed  
4 PILE CAP  PADANNA SIDE 8 8 Completed  
5 PIER CHERUVATHOOR SIDE 9 9 Completed  
6 PIER PADANNA SIDE 8 8 Completed  
7 PIER CAP CHERUVATHOOR SIDE 9 9 Completed  
8 PIER CAP PADANNA SIDE 8 8 Completed  
9 RE/RC WALL CHERUVATHOOR  SIDE 100% 100% Completed  
10 RE/RC  WALL PADANNA SIDE 100% 100% Completed  
11 BEAM/SLAB CHERUVATHOOR  SIDE 9 9 Completed RP3-P8 adjacent span girder and slab concreted.
12 BEAM/SLAB PADANNA SIDE 8 7 1 complete except railway adjacent span RP1-P7 Adjacent span STAGING WORK IP.
13 EXPANSION JOINT CHERUVATHUR SIDE 9 8 1 0 0 0 0 0 complete except P8
14 EXPANSION JOINT PADANNA SIDE 8 7 1 0 0 0 0 0 complete except P7
15 KERB CHERUVATHOOR  SIDE 100% 100.00% complete except railway adjacent span  
16 KERB PADANNA SIDE 100% 100% complete except railway adjacent span  
17 HANDRAIL CHERUVATHUR SIDE 100% 100% complete except railway adjacent span  
18 HANDRAIL PADANNA SIDE 100% 100% complete except railway adjacent span  
19 Painting 100% 100% Completed Painting complete except adjacent span.
17 BM/BC 100% 90% 10% 10% 0.00% 0.00% 0.00% 0.00% Bitumen works complete except Padanna side 4m road .
18 Others/Miscellaneous                 Drainage works complete for 150 m at chr side.
19 ROAD WORK GSB+WMM Work 100% complete  
20 Drainage Padanna side 100.00% 98.00% 2.00% 2.00% 0.00% 0.00% 2.00% 0.00% Drainage works 3m remaining.
                    DR Work complete for 4m service road and 7m road chr side.
21 RAILWAY PORTION  RP1-RP2 SPAN GIRDER AND SLAB CONCRETED.                        CENTRE SPAN DECK SLAB CONCRETED ON 28.04.14
 
Back
 
    
RAILWAY CENTRE SPAN

    
    
TOLL BOOTH WORK STARTED AT CHR SIDE

      
 

 

 

 

 

 

 

 

Untitled Document