   Weekly report as on 31.12.2010
    
Progress Report For Mulankunnathukavu ROB for the week ending on 31-12-2010
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  Remarks 
1 PILE SHORNUR  SIDE 9 9 0 0 0 0 0 0  
2 PILE M.C SIDE 36 36 0 0 0 0 0 0  
3 PILE CAP SHORNUR SIDE 3 0 3 0 3 1 2 0  
4 PILE CAP  M.C SIDE 12 8 4 0 1 4 0 *3 *work finished early
5 PIER SHORNUR  SIDE 3 0 3 0 0 0 0 0  
6 PIER M.C SIDE 12 4 8 0.5 3 5.5 0 2  
7 PIER CAP SHORNUR  SIDE 3 0 3 0 0 0 0 0  
8 PIER CAP M.C SIDE 12 0 12 0 0 0 0 1  
9 RE/R WALL SHORNUR  SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%  
10 RE/R WALL M.C SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%  
11 BEAM/SLAB SHORNUR  SIDE 3 0 3 0 0 0 0 0  
12 BEAM/SLAB M.C SIDE 12 0 12 0 0 0 0 0  
13 HR/FP/KERB SHORNUR  SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%  
14 HR/FP/KERB M.C SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%  
15 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%   
 
Back
 
    
PILE P10 SECOND LIFT CONCRETING27.12.2010

    
    
PILE P4 THIRD AND FINAL LIFT 28.12.2010

    
    
SHUTTERING FOR PIER CAP 29.12.2010

    
    
PILE CAP AP2 CONCRETING - 30.12.2010

    
 
    
SHUTTERING FOR PIER CAP 30.12.2010

    
    
REINFORCEMENT WORK FOR PILE CAP P1 - 31.12.2010

      
 

 

 

 

 

 

 

 