Prevoius Weekly Reports

   Weekly progress as on 06.06.2014
    
Sl No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  Remarks 
1 PILE MONTHAL BRIDGE SIDE 33 18 15 3 3 1 4 3 P12 location 1 pile concreted,delay due to DMC repair and lack of mud discharge pipe.
2 PILE NH SIDE 27 0 27            
3 PILE LOAD TEST 1 1 0 COMPLETE PILE LOAD TEST COMPLETE AT P15-1 LOCATION.
4 PILE CAP MONTHAL BRIDGE SIDE 9 0 9         1 P13 location planned.
5 PILE CAP  NH SIDE 7 0 7            
6 PIER MONTHAL BRIDGE SIDE 9 0 9            
7 PIER NH SIDE 7 0 7            
8 PIER CAP MONTHAL BRIDGE  SIDE 9 0 9            
9 PIER CAP NH SIDE 7 0 7            
10 RC WALL MONTHAL BRIDGE  SIDE 100% 0% 1            
11 RC  WALL NH SIDE 100% 0% 1            
12 GIRDER MONTHAL BRIDGE SIDE 9 0 9            
13 GIRDER NH SIDE 7 0 7            
14 DECK SLAB MONTHAL BRIDGE SIDE 9 0 9            
15 DECK SLAB NH SIDE 7 0 7            
16 EXPANSION JOINT MONTHAL BRIDGE SIDE 9 0 9            
17 EXPANSION JOINT NH SIDE 7 0 7            
18 KERB  MONTHAL BRIDGE  SIDE 9 0 9            
19 KERB NH SIDE 7 0 7            
20 HANDRAIL MONTHAL BRIDGE SIDE 9 0 9            
21 HANDRAIL NH SIDE 7 0 7            
22 Painting 100% 0% 100.00%            
23 ROAD WORK 100% 0% 100.00%            
24 BM/BC 100% 0% 100.00%            
25 Others/Miscellaneous   0 0            
26 Drainage  100.00% 0.00% 100.00%            
                     
27 RAILWAY PORTION  
                     
                     
                     
                     
  Availbility of Men                   
  Date 5/31/2014 6/1/2014 6/2/2014 6/3/2014 6/4/2014 6/5/2014 6/6/2014    
  No of labours 30 30 18 18 18 18 18    
 
Back
 
    
P13 LOCATION

    
    
P10-2 PILE CONCRETE

    
    
BORING IP AT P10-3

      
 

 

 

 

 

 

 

 