PROGRESS OF ROB ALOOR-MALA WORK AS ON 30-05-2014. |
|
Description |
Completed/ Progress |
Remarks |
1 |
ROB ALOOR-MALA |
|
|
1 |
Piling |
Completed. |
completed 32/32 |
2 |
Pilecap |
Completed. |
COMPLETED 8OUT OF 8 |
3 |
Pier |
Completed. |
completed 6out of 6. |
4 |
Piercap |
Completed. |
6 nos completed out of 6. |
5 |
Girder |
In progress |
5COPLETED OUT OF 6 |
6 |
Slab |
In progress |
3 completed out of 6. |
7 |
Handrail with kerb |
started |
Kerb 3 nos completed out of 6. |
8 |
Ex.joint |
Not started |
|
9 |
Tarring work |
Not started |
|
10 |
Diversion road |
In Progress |
aloor right side in progress 100% completed.Mala side LHS 100% |
11 |
Retaining wall worK |
started |
aloor side LHS completed,RHS started ,mala RHS WALL 50 M COMPLETED. |
12 |
Load test . |
Completed. |
In P4 location. |
13 |
Service road work |
started |
Aloor side LHS in progress.(slow progress) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|