Progress Report For Payyannur ROB for the week ending on 31-12-2010 |
Si No |
Activity Description |
Total Quantity |
Cumulative progress upto last week |
Balance work up to last week |
Cumulative delay in Qty up to last week |
Work planned during the week |
Actual work done during the week |
Cumulative delay in Qty up to this week |
Work Planned for next week |
Remarks |
1 |
PILE THRIKKARIPUR SIDE |
33 |
30 |
3 |
0 |
0 |
0 |
0 |
3 |
|
2 |
PILE EZHIMALA SIDE |
27 |
12 |
15 |
2 |
0 |
1 |
2 |
6 |
|
3 |
PILE PAYYANNUR SIDE |
27 |
19 |
8 |
0 |
0 |
2 |
0 |
3 |
|
4 |
PILE CAP THRIKKARIPUR SIDE |
11 |
6 |
5 |
1 |
0 |
2 |
0 |
0 |
|
5 |
PILE CAP EZHIMALA SIDE |
9 |
0 |
9 |
0 |
2 |
1 |
1 |
0 |
|
6 |
PILE CAP PAYYANNUR SIDE |
9 |
0 |
9 |
6 |
1 |
1 |
6 |
1 |
|
7 |
PIER THRIKKARIPUR SIDE |
11 |
4 |
7 |
1 |
1 |
1 |
1 |
1 |
|
8 |
PIER EZHIMALA SIDE |
9 |
0 |
9 |
0 |
0 |
0 |
0 |
1 |
|
9 |
PIER PAYYANNUR SIDE |
9 |
0 |
9 |
2 |
1 |
0 |
3 |
2 |
|
10 |
PIER CAP THRIKKARIPUR SIDE |
11 |
0 |
11 |
2 |
2 |
0 |
4 |
1 |
|
11 |
PIER CAP EZHIMALA SIDE |
9 |
0 |
9 |
0 |
0 |
0 |
0 |
0 |
|
12 |
PIER CAP PAYYANNUR SIDE |
9 |
0 |
9 |
0 |
1 |
0 |
1 |
0 |
|
13 |
RE/R WALL THRIKKARIPUR SIDE |
100% |
0 |
100% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
|
14 |
RE/R WALL EZHIMALA SIDE |
100% |
0 |
100% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
|
15 |
RE/R WALL PAYYANNUR SIDE |
100% |
0 |
100% |
6 |
0.00% |
0.00% |
100.00% |
0.00% |
|
16 |
BEAM/SLAB THRIKKARIPUR SIDE |
10 |
0 |
10 |
0 |
0 |
0 |
0 |
0 |
|
17 |
BEAM/SLAB EZHIMALA SIDE |
8 |
0 |
8 |
0 |
0 |
0 |
0 |
0 |
|
18 |
BEAM/SLAB PAYYANNUR SIDE |
9 |
0 |
9 |
0 |
0 |
0 |
0 |
0 |
|
19 |
HR/FP/KERB THRIKKARIPUR SIDE |
100% |
0 |
100% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
|
20 |
HR/FP/KERB EZHIMALA SIDE |
100% |
0 |
100% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
|
21 |
HR/FP/KERB PAYYANNUR SIDE |
100% |
0 |
100% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
|
22 |
BC/PAINTING |
100% |
0 |
100% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
|