Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 8053621
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   Weekly report as on 31.12.2010
    

 

Progress Report For Payyannur ROB for the week ending on 31-12-2010
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  Remarks 
1 PILE THRIKKARIPUR  SIDE 33 30 3 0 0 0 0 3  
2 PILE EZHIMALA SIDE 27 12 15 2 0 1 2 6  
3 PILE PAYYANNUR SIDE 27 19 8 0 0 2 0 3  
4 PILE CAP THRIKKARIPUR  SIDE 11 6 5 1 0 2 0 0  
5 PILE CAP EZHIMALA SIDE 9 0 9 0 2 1 1 0  
6 PILE CAP PAYYANNUR SIDE 9 0 9 6 1 1 6 1  
7 PIER THRIKKARIPUR  SIDE 11 4 7 1 1 1 1 1  
8 PIER EZHIMALA SIDE 9 0 9 0 0 0 0 1  
9 PIER PAYYANNUR SIDE 9 0 9 2 1 0 3 2  
10 PIER CAP THRIKKARIPUR  SIDE 11 0 11 2 2 0 4 1  
11 PIER CAP EZHIMALA SIDE 9 0 9 0 0 0 0 0  
12 PIER CAP PAYYANNUR SIDE 9 0 9 0 1 0 1 0  
13 RE/R WALL THRIKKARIPUR  SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%  
14 RE/R WALL EZHIMALA SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%  
15 RE/R WALL PAYYANNUR SIDE 100% 0 100% 6 0.00% 0.00% 100.00% 0.00%  
16 BEAM/SLAB THRIKKARIPUR  SIDE 10 0 10 0 0 0 0 0  
17 BEAM/SLAB EZHIMALA SIDE 8 0 8 0 0 0 0 0  
18 BEAM/SLAB PAYYANNUR SIDE 9 0 9 0 0 0 0 0  
19 HR/FP/KERB THRIKKARIPUR  SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%  
20 HR/FP/KERB EZHIMALA SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%  
21 HR/FP/KERB PAYYANNUR SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%  
22 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%   

 

 
Back
 
    
AP1 PIER HEAD SHUTTERING_P1P2P3P4(BEHIND) - 28.12.2010

    
    
P3&P4 PIERS - 29.12.2010

    
    
P3 IIND LIFT - 29.12.2010

    
    
P2 PIER - 29.12.2010

    
 
    
P1 PIER - 29.12.2010

    
    
P19 B BORING IN PROGRESS - 30.12.2010

    
    
P21&P22 PCC IN PROGRESS - 30.12.2010

    
 
    
P5 PILE CAP CONCRETING 30.12.2010

      
 

 

 

 

 

 

 

 

Untitled Document