Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 8118968
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   Weekly progress report as on 16.05.2014
    
Progress Report For Rob Kunhippalli for the week ending on 16-05-2014
Sl No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  Remarks 
1 PILE MONTHAL BRIDGE SIDE 33 12 21 3 3 2 3 3 P13 location 2piles concreted this week.
2 PILE NH SIDE 27 0 27            
3 PILE LOAD TEST 1 0 1            
4 PILE CAP MONTHAL BRIDGE SIDE 9 0 9            
5 PILE CAP  NH SIDE 7 0 7            
6 PIER MONTHAL BRIDGE SIDE 9 0 9            
7 PIER NH SIDE 7 0 7            
8 PIER CAP MONTHAL BRIDGE  SIDE 9 0 9            
9 PIER CAP NH SIDE 7 0 7            
10 RC WALL MONTHAL BRIDGE  SIDE 100% 0% 1            
11 RC  WALL NH SIDE 100% 0% 1            
12 GIRDER MONTHAL BRIDGE SIDE 9 0 9            
13 GIRDER NH SIDE 7 0 7            
14 DECK SLAB MONTHAL BRIDGE SIDE 9 0 9            
15 DECK SLAB NH SIDE 7 0 7            
16 EXPANSION JOINT MONTHAL BRIDGE SIDE 9 0 9            
17 EXPANSION JOINT NH SIDE 7 0 7            
18 KERB  MONTHAL BRIDGE  SIDE 9 0 9            
19 KERB NH SIDE 7 0 7            
20 HANDRAIL MONTHAL BRIDGE SIDE 9 0 9            
21 HANDRAIL NH SIDE 7 0 7            
22 Painting 100% 0% 100.00%            
23 ROAD WORK 100% 0% 100.00%            
24 BM/BC 100% 0% 100.00%            
25 Others/Miscellaneous   0 0            
26 Drainage  100.00% 0.00% 100.00%            
                     
27 RAILWAY PORTION  
                     
                     
                     
                     
  Availbility of Men                   
  Date 10-05-14 11-05-14 12-05-14 13-05-14 14-05-14 15-05-14 16-05-14    
  No of labours 10 10 10 10 10 10 10    
 
Back
 
    
RIGS AT P13 & P12 LOCATION

    
    
P13-1 PILE CONCRETE

    
    
JALLEY ERECTION P13 LOCATION

      
 

 

 

 

 

 

 

 

Untitled Document