Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 7887595
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   Weekly progress report as on 09.05.2014
    
Progress Report For Kumaranalloore ROB for the week ending on 09-5-2014  
Sl No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE 33 33 0 0 0 0 0       pile completed
2 PILE CAP 11 11 0 0 0 0 0       pile cap completed
3 PIER 11 11 0 0 0 0 0      pier completed
4 PIER CAP 11 11 0 0 0 0 0      pier cap completed
5 LOAD TEST 1 1 0 0 0 0 0     Load test completed
6 SLAB 8 8 0 0 0 0 0     slabs completed
7 PEDESTAL 9 9 0 0 0 0 0      
8 RETAINING WALL 4 1.5 2.5 0 0.2 0 0 0.2   kudamaloor side wall concreted c-section
9 ADJACENT SLAB 2 0 0 0 0 0 0     staging work started at kudamaloor side
                      expansion joint  and handrail work going on 
 
Back

No images are uploaded for this Weekly Reports

 
 
 

 

 

 

 

 

 

 

Untitled Document