Prevoius Weekly Reports

   Weekly report as on 24.12.2010
    

 

Progress Report For Mulankunnathukavu ROB for the week ending on 24-12-2010

Si No

Activity Description

Total Quantity

Cumulative progress upto last week

Balance  work up to last week

Cumulative delay in Qty up to last week

Work  planned  during the week

Actual work done during the week

Cumulative delay in Qty up to this week

Work  Planned for next week

Remarks

1

PILE SHORNUR  SIDE

9

9

0

0

0

0

0

0

 

2

PILE M.C SIDE

36

36

0

0

0

0

0

0

 

3

PILE CAP SHORNUR SIDE

3

0

3

0

0

0

0

3

 

4

PILE CAP  M.C SIDE

12

5

7

3

3

5

0

1

 

5

PIER SHORNUR  SIDE

3

0

3

0

0

0

0

0

 

6

PIER M.C SIDE

12

1.5

10.5

0

3

2.5

0.5

3

 

7

PIER CAP SHORNUR  SIDE

3

0

3

0

0

0

0

0

 

8

PIER CAP M.C SIDE

12

0

12

0

0

0

0

0

 

9

RE/R WALL SHORNUR  SIDE

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

10

RE/R WALL M.C SIDE

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

11

BEAM/SLAB SHORNUR  SIDE

3

0

3

0

0

0

0

0

 

12

BEAM/SLAB M.C SIDE

12

0

12

0

0

0

0

0

 

13

HR/FP/KERB SHORNUR  SIDE

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

14

HR/FP/KERB M.C SIDE

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

15

BC/PAINTING

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

  

 
Back
 
    
PIER P6 - FIRST LIFT CONCRETING - 18.12.2010

    
    
CHIPPING CONCRETE FOR PILE CAP - 20.12.2010

    
    
PIER P9 FIRST LIFT CONCRETING - 21.12.2010

    
    
PILE P3 SECOND LIFT CONCRETING - 22.12.2010

    
 
    
PILE P9 SECOND LIFT CONCREING - 23.12.2010

    
    
PILE P10 FIRST LIFT CONCRETING - 24.12.2010

      
 

 

 

 

 

 

 

 