Prevoius Weekly Reports

   Weekly progress report as on 25.04.2014
    
Progress as on 25-04-14
  Description Completed/ Progress Remarks
  ROB Kainatty (P6-RP4)    
1 Levelling and consolidation of the ground for staging work completed  
2 Staging work completed  
3 Reinforcement bending work completed  
4 Bottom shuttering work for girder completed  
5 Reinforcement binding for girder completed  
6 Shuttering work for girder completed  
7 Concreting of girder completed  
8 Shuttering work for deck slab completed  
9 Reinforcement binding of deck slab completed  
10 Deck slab concrete completed  
11 MISCELLANEOUS WORK completed  
11(a) Concreting of kerb, handrails completed  
11(b) Expansion joints completed  
12 ROAD WORK  completed  
12(a) Aplplying mastic Asphault completed  
12(b) Applying bituminous concrete completed  
13 PAINTING WORK completed  
 
  Description Completed/ Progress Remarks
  ROB Kainatty (P5-RP1)    
1 Levelling and consolidation of the ground for staging work completed  
2 Staging work completed  
3 Reinforcement bending work completed  
4 Bottom shuttering work for girder completed  
5 Reinforcement binding for girder completed  
6 Shuttering work for girder completed  
7 Concreting of girder completed  
8 Shuttering work for deck slab completed  
9 Reinforcement binding of deck slab completed  
10 Deck slab concrete completed  
11 MISCELLANEOUS WORK completed  
11(a) Concreting of kerb, handrails completed  
11(b) Expansion joints completed  
12 ROAD WORK completed  
12(a) Aplplying mastic Asphault completed  
12(b) Applying bituminous concrete completed  
13 PAINTING WORK completed  
       
  Description Completed/ Progress Remarks
  STAIRCASE-NADAPURAM  EAST SIDE    
1 Earthwork in excavation completed  
2 P.C.C for foundation completed  
3  Concreting of foundations completed  
4 Concreting of columns completed  
5 Concreting of flights completed  
6 Brick work  completed  
7 Plastering work completed  
8 Painting completed  
       
  Description Completed/ Progress Remarks
  STAIRCASE-NADAPURAM  WEST SIDE    
1 Earthwork in excavation completed  
2 P.C.C for foundation completed  
3  Concreting of foundations completed  
4 Concreting of columns completed  
5 Concreting of flights completed  
6 Brick work completed                                              
7 Plastering work completed  
8 Painting completed  
       
  STAIRCASE-KAINATTY  EAST SIDE    
1 Earthwork in excavation completed  
2 P.C.C for foundation completed  
3  Concreting of foundations completed  
4 Concreting of columns completed  
5 Concreting of flights completed  
6 Brick work completed  
7 Plastering completed  
8 Painting completed  
       
  TOLL BOOTH    
1 Earthwork in excavation completed  
2 P.C.C for foundation completed  
3 Concreting of foundations completed  
4 Concreting of Lintel completed  
4 Brick work completed  
5 Plastering Not Started Planned for next Wednesday after deshuttering the supports of roof slab
6 Concreting of roof slab completed  
7 Painting Not Started  
       
 