Prevoius Weekly Reports

   Weekly Progress report as on 24/12/2010
    

                    

Progress Report For Kainatty ROB for the week ending on 24-12-2010

Si No

Activity Description

Total Quantity

Cumulative progress upto last week

Balance  work up to last week

Cumulative delay in Qty up to last week

Work  planned  during the week

Actual work done during the week

Cumulative delay in Qty up to this week

Work  Planned for next week

Remarks

1

PILE KAINATTY  SIDE

18

10

8

2

3

2

3

0

 

2

PILE NADAPURAM SIDE

27

8

19

0

3

5

0

6

 

3

PILE CAP KAINATTY SIDE

6

0

6

1

1

0

2

0

 

4

PILE CAP  NADAPURAM SIDE

9

0

9

0

0

0

0

1

 

5

PIER KAINATTY  SIDE

6

0

6

0

1

0

1

0

 

6

PIER NADAPURAM SIDE

9

0

9

0

0

0

0

0

 

   

 
Back
 
    
PILING IN PROGRESS (21/12/2010)

    
    
CONCRETING OF AP1 (21/12/2010)

    
    
CONCRETING OF AP1 (21/12/2010)

    
    
PILING IN PROGRESS (21/12/2010)

    
 
    
REINFORCEMENTS STACKED AT THE SITE (21/12/2010)

    
    
WORK IN PROGRESS FOR ERECTING REINFORCEMENT FOR PILE (21/12/2010)

      
 

 

 

 

 

 

 

 