Progress as on 18-04-14 |
|
Description |
Completed/ Progress |
Remarks |
|
ROB Kainatty (P6-RP4) |
|
|
1 |
Levelling and consolidation of the ground for staging work |
completed |
|
2 |
Staging work |
completed |
|
3 |
Reinforcement bending work |
completed |
|
4 |
Bottom shuttering work for girder |
completed |
|
5 |
Reinforcement binding for girder |
completed |
|
6 |
Shuttering work for girder |
completed |
|
7 |
Concreting of girder |
completed |
|
8 |
Shuttering work for deck slab |
completed |
|
9 |
Reinforcement binding of deck slab |
completed |
|
10 |
Deck slab concrete |
completed |
|
11 |
MISCELLANEOUS WORK |
completed |
|
11(a) |
Concreting of kerb, handrails |
completed |
|
11(b) |
Expansion joints |
completed |
|
12 |
ROAD WORK |
In progress |
|
12(a) |
Aplplying mastic Asphault |
completed |
|
12(b) |
Applying bituminous concrete |
Not started |
Arranged for 21st april 2014 |
13 |
PAINTING WORK |
completed |
|
|
|
Description |
Completed/ Progress |
Remarks |
|
ROB Kainatty (P5-RP1) |
|
|
1 |
Levelling and consolidation of the ground for staging work |
completed |
|
2 |
Staging work |
completed |
|
3 |
Reinforcement bending work |
completed |
|
4 |
Bottom shuttering work for girder |
completed |
|
5 |
Reinforcement binding for girder |
completed |
|
6 |
Shuttering work for girder |
completed |
|
7 |
Concreting of girder |
completed |
|
8 |
Shuttering work for deck slab |
completed |
|
9 |
Reinforcement binding of deck slab |
completed |
|
10 |
Deck slab concrete |
completed |
|
11 |
MISCELLANEOUS WORK |
completed |
|
11(a) |
Concreting of kerb, handrails |
completed |
|
11(b) |
Expansion joints |
completed |
|
12 |
ROAD WORK |
In progress |
|
12(a) |
Aplplying mastic Asphault |
completed |
|
12(b) |
Applying bituminous concrete |
Not started |
Arranged for 21st april 2014 |
13 |
PAINTING WORK |
completed |
|
|
|
|
|
|
Description |
Completed/ Progress |
Remarks |
|
STAIRCASE-NADAPURAM EAST SIDE |
|
|
1 |
Earthwork in excavation |
completed |
|
2 |
P.C.C for foundation |
completed |
|
3 |
Concreting of foundations |
completed |
|
4 |
Concreting of columns |
completed |
|
5 |
Concreting of flights |
completed |
|
6 |
Brick work |
completed |
|
7 |
Plastering work |
completed |
|
8 |
Painting |
In progress |
First coat in progress |
|
|
|
|
|
Description |
Completed/ Progress |
Remarks |
|
STAIRCASE-NADAPURAM WEST SIDE |
|
|
1 |
Earthwork in excavation |
completed |
|
2 |
P.C.C for foundation |
completed |
|
3 |
Concreting of foundations |
completed |
|
4 |
Concreting of columns |
completed |
|
5 |
Concreting of flights |
completed |
|
6 |
Brick work |
completed |
|
7 |
Plastering work |
completed |
|
8 |
Painting |
In progress |
First coat in progress |
|
|
|
|
|
STAIRCASE-KAINATTY EAST SIDE |
|
|
1 |
Earthwork in excavation |
completed |
|
2 |
P.C.C for foundation |
completed |
|
3 |
Concreting of foundations |
completed |
|
4 |
Concreting of columns |
completed |
|
5 |
Concreting of flights |
completed |
|
6 |
Brick work |
completed |
|
7 |
Plastering |
completed |
|
8 |
Painting |
In progresss |
First coat in progress |
|
|
|
|
|
TOLL BOOTH |
|
|
1 |
Earthwork in excavation |
completed |
|
2 |
P.C.C for foundation |
completed |
|
3 |
Concreting of foundations |
completed |
|
4 |
Concreting of Lintel |
completed |
|
4 |
Brick work |
In Progress |
Finished upto Lintel level |
5 |
Plastering |
Not Started |
|
6 |
Concreting of roof slab |
Not Started |
|
7 |
Painting |
Not Started |
|