   Weekly progress report as on 18.04.2014
    
Progress as on 18-04-14
  Description Completed/ Progress Remarks
  ROB Kainatty (P6-RP4)    
1 Levelling and consolidation of the ground for staging work completed  
2 Staging work completed  
3 Reinforcement bending work completed  
4 Bottom shuttering work for girder completed  
5 Reinforcement binding for girder completed  
6 Shuttering work for girder completed  
7 Concreting of girder completed  
8 Shuttering work for deck slab completed  
9 Reinforcement binding of deck slab completed  
10 Deck slab concrete completed  
11 MISCELLANEOUS WORK completed  
11(a) Concreting of kerb, handrails completed  
11(b) Expansion joints completed  
12 ROAD WORK  In progress  
12(a) Aplplying mastic Asphault completed  
12(b) Applying bituminous concrete Not started Arranged for 21st april 2014
13 PAINTING WORK completed  
 
  Description Completed/ Progress Remarks
  ROB Kainatty (P5-RP1)    
1 Levelling and consolidation of the ground for staging work completed  
2 Staging work completed  
3 Reinforcement bending work completed  
4 Bottom shuttering work for girder completed  
5 Reinforcement binding for girder completed  
6 Shuttering work for girder completed  
7 Concreting of girder completed  
8 Shuttering work for deck slab completed  
9 Reinforcement binding of deck slab completed  
10 Deck slab concrete completed  
11 MISCELLANEOUS WORK completed  
11(a) Concreting of kerb, handrails completed  
11(b) Expansion joints completed  
12 ROAD WORK In progress  
12(a) Aplplying mastic Asphault completed  
12(b) Applying bituminous concrete Not started Arranged for 21st april 2014
13 PAINTING WORK completed  
       
  Description Completed/ Progress Remarks
  STAIRCASE-NADAPURAM  EAST SIDE    
1 Earthwork in excavation completed  
2 P.C.C for foundation completed  
3  Concreting of foundations completed  
4 Concreting of columns completed  
5 Concreting of flights completed  
6 Brick work  completed  
7 Plastering work completed  
8 Painting In progress First coat in progress
       
  Description Completed/ Progress Remarks
  STAIRCASE-NADAPURAM  WEST SIDE    
1 Earthwork in excavation completed  
2 P.C.C for foundation completed  
3  Concreting of foundations completed  
4 Concreting of columns completed  
5 Concreting of flights completed  
6 Brick work completed                                              
7 Plastering work completed  
8 Painting In progress First coat in progress
       
  STAIRCASE-KAINATTY  EAST SIDE    
1 Earthwork in excavation completed  
2 P.C.C for foundation completed  
3  Concreting of foundations completed  
4 Concreting of columns completed  
5 Concreting of flights completed  
6 Brick work completed  
7 Plastering completed  
8 Painting In progresss First coat in progress
       
  TOLL BOOTH    
1 Earthwork in excavation completed  
2 P.C.C for foundation completed  
3 Concreting of foundations completed  
4 Concreting of Lintel completed  
4 Brick work In Progress Finished upto Lintel level
5 Plastering Not Started  
6 Concreting of roof slab Not Started  
7 Painting Not Started  
 