Prevoius Weekly Reports

   weekly progress as on 24.12.2010
    

 

SlNo

Activity -Description

Total Quantity

Cumulative progress up to this week

(1)

Balance  work

(2)

Cumulative delayin weeks after

Spplagmnt

(3)

Work  planned  during the week

(4)

Actual work done during the last week

(5)

Short fall in the last week 

(6)

Work  Planned for next week

(7)

Remarks

1

Re wall towards NH side

100%

0

100

16

0

0

0

0

 

2

RE wall towards Pulikkakadavuside

100%

99

2

36

1

1

-

1

 

3

Approach

 Span

5 No

4

1

25

-

-

-

-

 

4

Railway

 span

3No

0

0

23

 

 

 

 

 

5

Pile (Rly)

18No

Piling arrangement for Pier P2 started

 

18

43

 

 

 

 Balance portion of Boring

 

6

Piers (Rly)

4No

0

0

33

 

 

 

 

 

7

 

Handrail towards pulikakakdavu side

 

426

87m

339

 

 

 15

 0

 55

 

8

Kerb

639

248

391

-

 

 29

 

 70

 

9

Road work

100%

0

0

 

 

 

 

 

 

10

Friction slab towards pulikkakadavu side

128

35

93

 

15

15

0

 55

 

11

Approachslab

 

2 No

1

 

 

 

 

 

 

 

 

12

Cap Beam

128m

108m

 20

 

 

 

 

 20

 

 

DATE 18-12-2010 20-12-2010 21-12-2010 22-12-2010 23-12-2010 24-12-2010
LABOUR 8 18 25 26 30 26
CLIMATE SUNNY SUNNY SUNNY SUNNY SUNNY SUNNY 
 
Back
 
    
TRIPOD ARRANGEMENT FOR PILING

    
    
REINFORCEMENT FOR FRICTION SLAB 21.12.2010

    
    
REINFORCEMENT FOR FRICTION SLAB 20.12.2010

    
    
HAND RAIL 22.12.2010

    
 
    
PILE BORING 23.12.2010

    
    
PANEL LEVEL CONCRETING 18.12.2010

    
    
MATERIALS FOR PILING 18.12.2010

    
 
    
HAND RAIL 22.12.2010

    
    
FRICTION SLAB CONCRETING 23.12.2010

    
    
FRICTION SLAB CONCRETING 22.12.2010

    
 
    
EXCAVATION FOR PILE P2 20.12.2010

      
 

 

 

 

 

 

 

 