   Weekly progress report as on 04.04.2014
    
PROGRESS OF ROB ALOOR-MALA  WORK AS ON 04-04-2014.
  Description Completed/ Progress Remarks
1 ROB ALOOR-MALA    
1 Piling Completed. completed 32/32
2 Pilecap Completed. COMPLETED 8OUT OF 8
3 Pier Completed. completed 6out of 6.
4 Piercap Completed. 6 nos completed out of 6.
5 Girder In progress P1-P2,A1-P1 ,P3-P4  COMPLETED,P6-A2 IN PROGRESS.
6 Slab In progress P1-P2  completed
7 Handrail with kerb  started Kerb p1-p2 completed.
8 Ex.joint Not started  
9 Tarring work Not started  
10 Service road work(Diversion road)  In Progress aloor right side in progress 100% completed.Mala side LHS 100%
11 Retaining wall worK  started aloor side LHS WALL 90% COMPLETED   ,mala side WALL 50 M COMPLETED. 
12 Load test . Completed. In P4 location.
       
       
       
       
       
       
       
 