Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 8051500
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   Weekly progress report as on 04.04.2014
    
Progress as on 04-04-14
  Description Completed/ Progress Remarks
  ROB Kainatty (P6-RP4)    
1 Levelling and consolidation of the ground for staging work completed  
2 Staging work completed  
3 Reinforcement bending work completed  
4 Bottom shuttering work for girder completed  
5 Reinforcement binding for girder completed  
6 Shuttering work for girder completed  
7 Concreting of girder completed  
8 Shuttering work for deck slab completed  
9 Reinforcement binding of deck slab completed  
10 Deck slab concrete completed  
11 MISCELLANEOUS WORK completed  
11(a) Concreting of kerb, handrails completed  
11(b) Expansion joints completed  
12 ROAD WORK  In progress  
12(a) Aplplying mastic Asphault completed  
12(b) Applying bituminous concrete Not started  
13 PAINTING WORK completed  
 
  Description Completed/ Progress Remarks
  ROB Kainatty (P5-RP1)    
1 Levelling and consolidation of the ground for staging work completed  
2 Staging work completed  
3 Reinforcement bending work completed  
4 Bottom shuttering work for girder completed  
5 Reinforcement binding for girder completed  
6 Shuttering work for girder completed  
7 Concreting of girder completed  
8 Shuttering work for deck slab completed  
9 Reinforcement binding of deck slab completed  
10 Deck slab concrete completed  
11 MISCELLANEOUS WORK completed  
11(a) Concreting of kerb, handrails completed  
11(b) Expansion joints completed  
12 ROAD WORK In progress  
12(a) Aplplying mastic Asphault completed  
12(b) Applying bituminous concrete Not started  
13 PAINTING WORK In progress 1st coat completed
       
  Description Completed/ Progress Remarks
  STAIRCASE-NADAPURAM  EAST SIDE    
1 Earthwork in excavation completed  
2 P.C.C for foundation completed  
3  Concreting of foundations completed  
4 Concreting of columns completed  
5 Concreting of flights completed  
6 Brick work  completed  
7 Plastering work completed  
       
  Description Completed/ Progress Remarks
  STAIRCASE-NADAPURAM  WEST SIDE    
1 Earthwork in excavation completed  
2 P.C.C for foundation completed  
3  Concreting of foundations completed  
4 Concreting of columns completed  
5 Concreting of flights completed  
6 Brick work completed                                              
7 Plastering work completed  
       
  STAIRCASE-KAINATTY  EAST SIDE    
1 Earthwork in excavation completed  
2 P.C.C for foundation completed  
3  Concreting of foundations completed  
4 Concreting of columns completed  
5 Concreting of flights completed  
6 Brick work completed  
7 Plastering completed  
       
  TOLL BOOTH    
1 Earthwork in excavation completed  
2 P.C.C for foundation completed  
3 Concreting of foundations completed  
4 Brick work Not Started  
5 Plastering Not Started  
6 Concreting of roof slab Not Started  
7 Painting Not Started  
       
 
Back

No images are uploaded for this Weekly Reports

 
 
 

 

 

 

 

 

 

 

Untitled Document