   Weekly progress report as on 04.04.2014
    
Progress Report For Palakkad Sultanpet ROB for the week ending on 04-04-2014
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PCC for RAFT MOYAN SIDE 3 3 0 0 0 0 0 0    
2 PCC for RAFT PALAKKAD SCHOOL SIDE 1 1 0 0 0 0 0 0    
3 RAFT PALAKKAD SIDE 1 1 0 0 0 0 0 0    
4 RAFT MOYAN SCHOOL SIDE 3 3 0 0 0 0 0 0    
5 PIER PALAKKAD SIDE 1 1 0 0 0 0 0 0    
6 PIER MOYAN SCHOOL SIDE 3 3 0 0 0 0 0 0    
7 PIER CAP PALAKKAD SIDE 1 1 0 0 0 0 0 0    
8 PIER CAP MOYAN SCHOOL SIDE 3 3 0 0 0 0 0 0    
9 RE/R WALL PALAKKAD  SIDE 100% 100% 0% 0 0.00% 0.00% 0.00% 0.00%    
10 RE/R WALL MOYAN SCHOOL SIDE 100% 100% 0% 0 0.00% 0.00% 0.00% 0.00%    
11 BEAM/SLAB  Staging Palakad  SIDE 2 2 0 0 0 0 0 0    
12 BEAM/SLAB  Bar bending and Fixing Palakad  SIDE 2 2 0 0 0 0 0 0    
13 BEAM/SLAB  Shuttering  and Concreting Palakad SIDE 2 2 0 0 0 0 0 o    
14 BEAM/SLAB  Staging Moyan schoolSIDE 4 4 0 0 0 0 0 0    
15 BEAM/SLAB  Bar bending and Fixing Moyan school SIDE 4 4 0 0 0 0 0 0    
16 BEAM/SLAB  Shuttering  and Concreting  Moyan school  SIDE 4 4 0 0 0 0 0 0    
17 BEAM/SLAB PALAKKAD  SIDE 2 2 0 0 0 0 0 0    
18 BEAM/SLAB MOYAN SCHOOL SIDE 4 4 0 0 0 0 0 0    
19 BEAM/SLAB RAILWAY SPAN 6 6 0 0 0 0 0 0    
20 HR/FP/KERB Pkd  SIDE 100% 100% 0% 0 0.00% 0.00% 0.00% 0.00%    
21 HR/FP/KERB Moyen's SIDE 100% 100% 0% 0 0.00% 0.00% 0.00% 0.00%    
22 HR/FP/KERB RAILWAY SPAN 100% 83% 17% 0 3.00% 3.00% 0.00% 2.00%    
23 BC/PAINTING 100% 70% 30% 0 0.00% 0.00% 0.00%      
 
Back
 
    
RP3-RP4 CRASH BARRIER AND PARAPET WALL

    
    
BOWSTRING CLEANING AND MASTIC WORK

    
    
BOWSTRING CLEANING AND MASTIC WORK

      
 

 

 

 

 

 

 

 