Prevoius Weekly Reports

   Weekly progress as on 04.04.2014
    
Sl No   Activity Description   Total Quantity  Cumulative progress  Balance  work  Cumulative delay in Qty  Work  planned  during the week   Actual work done during the week   Cumulative delay in Qty up to this week  Work  Planned for next week  
1 Pile  60 3 57    3 2 1 3
2 Pile Load Test  1 0 1              
3 Pilecap  18 0 18              
4 Pier  18 0 18              
5 Piercap  18 0 18              
6 Girders  16 0 16            
7 Deckslab  16 0 16            
8 Handrails & footpath slab casting  100% 0% 100%              
9 Retaining Wall NH side  100% 0% 100%              
10 Retaining Wall Mondhal Bridge side  100% 0% 100%              
11 Road work NH side  100% 0% 100%              
12 Road work Mondhal Bridge side  100% 0% 100%              
 